Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

ATTREX 02/06/15 Mission Daily Schedule

Overview:

  • CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25 
  • GHOST installation continues Saturday

Accomplishments:

  • AIITS Pod mounting on the wing completed
  • Structural Shear/Bending Analysis review meeting held at NGC
  • Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.

Concerns / Watch List:

  • AIITS Diode Laser replacement has been shipped – expected at AFRC on Monday
  • Reviewing need for laser-replacement waiver
  • NGC Shear/Bending analysis by NGC now suspected to be in error, analysis to be corrected
  • GHOST integration continues Saturday to get on schedule

Upcoming Schedule:

  • Tomorrow, Saturday: GHOST Pallet installation continues
  • Monday:
    • GHOST avionics harness installation
    • Begin Data-IT Hangar Testing of all instruments on aircraft power