Daily Schedule

0700 - 1500 ER2 Crew support
0700 - Lab access with FN escort (3 FN escorts needed)
1300 - Navigation data check
PALMS
Working software updates and calibration.
UCATS
Mostly finished integration.
Need to route inlet lines from bottom rack to the top rack. This will be completed after HUPCRS arrives for integration.
CAFE/CANOE/ROZE
Weight and balance done.
Troubleshooting ROZE power configuration.
ER2
Tyler is working the pilot checklist. He will send (~ 2 weeks) the checklist spread-sheet to the PI for review.

  • 0700 - 1500 ER2 crew support
  • 0700 Lab Access
  • Two designated FN escorts and one backup needed

0800 - 1200 DPOPS, Lab access, with escort.

It's been another productive day. Accomplishments:

UCATS

  • Drill-matched the aircraft mount frame
  • Finished lab set up
  • Calibration work

PALMS

  • Finished laser calibration

DPOPS

  • Calibration work
  • Solved remote SSH access to instrument

Looking ahead, UCATS will access the lab over the weekend. DPOPS lab access Saturday morning, rest Sunday. 

Late Friday, NASA Headquarters released guidance regarding mask wearing for COVID-19 vaccinated people. The new guidance aligns with the new CDC recommendations. However, until we receive updated information from the NASA AFRC center, the DCOTSS participants will continue to wear N95 masks while on-site and working closer than 6' from each other for any amount of time.

0800 - 1200 DPOPS, Lab access, with escort.

It's been another productive day. Accomplishments:

UCATS

  • Drill-matched the aircraft mount frame
  • Finished lab set up
  • Calibration work

PALMS

  • Finished laser calibration

DPOPS

  • Calibration work
  • Solved remote SSH access to instrument

Looking ahead, UCATS will access the lab over the weekend. DPOPS lab access Saturday morning, rest Sunday. 

Late Friday, NASA Headquarters released guidance regarding mask wearing for COVID-19 vaccinated people. The new guidance aligns with the new CDC recommendations. However, until we receive updated information from the NASA AFRC center, the DCOTSS participants will continue to wear N95 masks while on-site and working closer than 6' from each other for any amount of time.

0700 - 1500 Lab access with ER2 support
1330 - DPOPS comm. work with Carl Sorenson 
1200 - DCOTSS all-hands meeting
1300 - COVID training for those who did not attend before (remote Teams meeting)

Achievements

PALMS and DPOPS

  • final integrated instrument fit check with full connections
  • integrated power-up test
  • plumbing leak test (run instruments with filters over inlets)
  • particles detection on PALMS (after removing filters)
  • Internet access worked out for DPOPS

MMS

  • fully integrated, final power test, and comm. test
  • Paul will go home tomorrow to return prior to check flights

UCATS

  • Fred and Eric arrived today and got badged.
  • Mask fit check tomorrow

ESPO

  • Leslie Ryan arrived today and worked with Caitlin to take over her duties
  • Caitlin is leaving tomorrow. She will return in two weeks Thank you Caitlin for the excellent work!
Goals

PALMS

  • Lab work

DPOPS

  • working instrument internet connections

UCATS

  • setup workspace
  • receive cargo
  • start integration

POD
0700 – 1500 ER2 Support
0700 – Lab Access
0800 – PALMS & DPOPS access to A/C nose for a fit check

Achievements
MMS 
Identified and fixed power harness issue

DPOPS
Instrument work
New team member arrival

PALMS
Laser calibration work.

Goals
MMS 
Finish electrical power check 
Networking work

            DPOPS
Calibration
Fit check

            PALMS
Fit check 
Continue laser calibration

0700 — 1500 ER2 support and Lab access (as long as needed)
0730 — Yaowei badging
0800 — Yaowei mask fitting, room S241. 

Achievements

DPOPS 
- Final fit check 
- Finished plumbing 
- Electric check with EIP

PALMS
- Connected to the two inlets
- Weight & balance the nose

MMS 
- integration work in the fixed nose area of the aircraft

Goals for Tuesday

DPOPS 
- particle size calibration
- welcome new team member

PALMS
- laser alignment 
- software work with remote access

MMS
- Power checks with aircraft power in both fixed and removable nose areas

0700 - 1500 Lab access and ER2 support

0700 – 1500 Lab access only, no ER2 support required.

0900 PALMS / FN escorts (ESPO)

 

May 9, 2021 – Rest day

0700 - 1500 Lab access 
0800 - 1500 A/C crew support (or, as long as needed)
Achievements and goals

PALMS 
-- troubleshoot A/C power cable pinout
-- successfully powered up from 120V supply
-- repositioned two top components, eliminated all mechanical interferences. 
-- test powering up from the EIP (i.e., aircraft power simulator)

DPOPS
-- DPOPS plumbing work
-- continue plumbing manifold work tomorrow

MMS
-- integration work in the fixed nose area (on the aircraft)
--built new cables

Other
Today, LA county moved to the yellow tier. This is good news as far as total COVID-19 case numbers, however, no expected changes to our working conditions.