ATTREX

ATTREX 02/13/15 Mission Daily Schedule
Overview:
  • All instruments are now integrated on the aircraft
  • Outdoor Satcom Testing has begun
Accomplishments:
  • Outdoor Satcom testing, with Instrument teams in the GHOC has begun
  • NOAA O3 and NWV, MTP, and GWAS complete Iridium testing
  • All four instruments are complete with no testing planned on Tuesday
  • MMS, Hawkeye, AIITS testing has begun
Issues/Watch items:
  • No Ku Satcom Testing accomplished - the GH Ku Ground Terminal at Wallops was offline (a weather, alignment issue)
ATTREX 02/17/15 Mission Daily Schedule
Overview:
  • MMS and GHOST wiring issues resolved, outdoor Satcom Testing continues tomorrow.
  • Expectation of Pre-CST by COB tomorrow.
  • P.I.’s - see arrival schedule below to support testing and Pre-CST
Accomplishments:
  • NGC reports CAST/ATTREX payload passes shear-bending analysis
  • GHOST Cryostat cool-down and re-installation on aircraft
  • MMS wiring and GHOST IT issues resolved
  • Tech Brief Slide run-through
  • Weekly CAST/ATTREX Leads Telecom
Issues/Watch items:
  • MM

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.