ATTREX 02/13/15 Mission Daily Schedule

Overview:
  • All instruments are now integrated on the aircraft
  • Outdoor Satcom Testing has begun
Accomplishments:
  • Outdoor Satcom testing, with Instrument teams in the GHOC has begun
  • NOAA O3 and NWV, MTP, and GWAS complete Iridium testing
  • All four instruments are complete with no testing planned on Tuesday
  • MMS, Hawkeye, AIITS testing has begun
Issues/Watch items:
  • No Ku Satcom Testing accomplished - the GH Ku Ground Terminal at Wallops was offline (a weather, alignment issue)
  • System needs to be online next Tuesday & Wednesday to stay on schedule
  • Discovered a Data-Ethernet connectivity issue to GHOST, suspected to Payload System based
  • Therefore, Tuesday will begin with additional Hangar IT Testing to troubleshoot
  • Most of Tuesday and all of Wednesday will be used for additional outdoor Satcom testing - to be concluded with the Pre-CST.

Upcoming Schedule:

No P.I. activity in the GH Hangar Sat or Sun or Monday (Holiday). GHOST LN2 Cryo servicing to be performed as scheduled.

Tuesday
  • Begin the morning in the Hangar – troubleshoot GHOST Data-ethernet connectivity issue
  • Aircraft outdoors for Satcom testing when GHOST IT issue resolved
  • Wallops Ku Ground Terminal needed for testing
  • MMS, Hawkeye, AIITS, MTP, GHOST Inst. Teams needed at 0900 (report to Hangar first)
  • NOAA O3, NWV, GWAS, and MTP Team are not needed Tuesday
Wednesday
  • Aircraft outdoors for Satcom Testing, all Inst. Teams needed in GHOC
  • Pre-CST Test, as scheduled.

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.