IMPACTS 01/13/20 Mission Daily Schedule

IMPACTS General
TUESDAY, JAN 14
*10:00:11:00*: Daily Briefing (Wallops W162; Webex/Telecon)
WEDNESDAY, JAN 15
09:00-10:00: Daily Briefing (Wallops W162; Webex/Telecon)
10:00-11:00: All-Hands Mission Kick-Off & Safety Briefing (WFF/ Hunter AAF separate meetings)

IMPACTS P-3 - Wallops
TUESDAY, JAN 14
*Test Flight Canceled*
Media Day at NASA WFF
08:00-14:30: Aircraft access with power
WEDNESDAY, JAN 15
Safety Brief (TBD new folks only)
08:00-11:00: Aircraft access with power
Test Flight Day (Timing TBD)

IMPACTS ER-2 - Hunter
TUESDAY, JAN 14
Finish Hangar Setup 
WEDNESDAY, JAN 15
12:00: ER-2 Transit to Hunter

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.