We are finally here! Our first plan of the day for the IMPACTS 2020 field deployment.
IMPACTS General
Now that everyone is starting their journey to Wallops and Hunter, don’t forget to review our deployment guides. During the next few days the teams will be getting situated at the ops centers in Wallops and Hunter. Please coordinate with ESPO if you have any questions and/or concerns. All times below are Easter Standard Time.
- WEDNESDAY, JAN 08, 2020:
- Lynn arrives at Wallops
- 1100: General status meeting (Wallops W162; Webex/Telecon)
- THURSDAY, JAN 09, 2020:
- General access day
- 1100: General status meeting (Wallops W162; Webex/Telecon)
- FRIDAY, JAN 10, 2020:
- General access day
- 1100: General status meeting (Wallops W162; Webex/Telecon)
- 1600: Pre-forecasting meeting (Wallops W162; Webex/Telecon)
- SATURDAY, JAN 11, 2020:
- 1100: General status meeting (Wallops W162; Webex/Telecon)
IMPACTS P-3 - Wallops
- WEDNESDAY, JAN 08, 2020:
- General access day
- THURSDAY, JAN 09, 2020:
- General access day
- FRR (TBD)
- FRIDAY, JAN 10, 2020:
- General access day
- ATP (TBD)
- SATURDAY, JAN 11, 2020:
- Test flights (TBD)
IMPACTS ER-2 - Hunter
- WEDNESDAY, JAN 08, 2020:
- ER-2 Equipment Departs Palmdale
- THURSDAY, JAN 09, 2020:
- Night Proficiency flights (2x)
- FRIDAY, JAN 10, 2020:
- RDO / Science Equipment Departs Palmdale
- SATURDAY, JAN 11, 2020:
- Crew down day
ESPO Crew on deck
Wallops: Vidal Salazar (650 499-6405), Katie Stern (650 440 8749)
Hunter: Quincy Alison (650 455-4964), Brent Williams (831 247-8242)