Overview:
- AV-1 Successful Range Flight (see below)
- AV-6 Transit Flt. prep. continues
Today’s Accomplishments:
- AV-1 completed a successful Range flight but did have a
Link mod failure just before descent and also had issues
with the radar altimeter during landing (troubleshooting in
progress). Both Low-light and Daylight Cameras worked and
Instrument data downloads completed
- AV-6 Nose Gear swing test was complete and remaining
tests should be completed tomorrow.
- HS3 Dry Run continued
Plan for Friday – AV-1 Range Flight (Times shown are local)
- AFRC (PDT):
o Continued troubleshooting on AV-1
o Landing gear tests continued on AV-6
o 0800: HS3 HQ MRR
o 0800: Dry Run continues
o Instrument Access
- WFF (EDT):
o 1100: HS3 HQ MRR
o 1100: Dry Run continues