Overview:
- AV-1 prepped for CST
- AV-6 being prepped for Transit Flt. next week
Today’s Accomplishments:
- HIRAD and HAMSR re-installed and tested
- Preflight prep of all instruments & Aircraft for CST
- AV-6 HDVis camera wiring issue identified, being repaired
- Both new Low-light cameras delivered, being tested
- HS3 Dry Run continues
Plan for Tuesday – AV-6 CST (Times shown are local)
- AFRC (PDT):
o 0630: CST Briefing (Payload Cage)
o 0745: Crew step in GHOC
o 0800: Engine Start for CST
o 0800: Dry Run continues
0800 – ~1000: CST
- WFF (EDT):
o 0930: CST Briefing
o 1030: P.I.’s in GHOC-E
o 1100: Engine Start for CST
o 1100 - ~1300: CST
o 1100: Dry Run continues
Plan for Wednesday – Instrument Pre-flight
- 0730 PDT: Power-on Aircraft for Instrument Pre-flight
o Data-IT and Avionics support
o HIRAD, HAMSR, HIRAD please report at 0730
- 0745 PDT: CST Preflight Debrief
- 0800 PDT (1100 EDT): Dry Run Continues
- 1100 Range Flight T-1
Outlook:
- Thur.: AV-1 Range Flight
o 0500 PDT: T-0 Flight Briefing
o 0630 PDT: Takeoff
- Fri: HS3 MRR (WebEx and Phone)
- 19-20 Aug: AV-1 Transit to WFF (overnight flight)
- 21-22 Aug: AV-6 Transit to WFF (overnight flight)