ATTREX 02/21/14 Daily Schedule

ATTREX  GH Overview:

-Ku Satcom on the GH is now operational

-Awaiting the arrival of replacement Engine Bypass Valve

-Next Flight is Sunday, 23Feb – ~0140 Engine Start, 0225 T.O.

Today’s Activities:

-0730: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

- Ku Satcom Testing with aircraft and PMOF – Operational for next flight

-UCATS and NOAA H2O removed pending pre-flight for next flight

Plan for Saturday:

-0730: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

- Instrument Pre-flight (note the two periods, below):

o   For instruments NOT NEEDING aircraft Power or Data-IT:

 §  0700 – 1200: Preflight of Instruments

o   For instruments NEEDING aircraft Power and Data-IT:

 §  2000 – 2200: Preflight of Instruments

-Instrument Pre-launch Preflight by DLH, DOAS, PCRS:

o   1900 – 2200: “Day-of-Flight” Inst. Pre-flight activity

Plan for Sunday (Science Flight #3):

-0030: T-0 Briefing (to be held in the GH Crew Area, Hangar)

o   0125: Staff PMOF

- 0140: Engine Start

o0205: Pin-Pull

-~0225: Taxi and Take-off

-  ~2100: Landing (~18.5-hr flight)

- 2100 – 0400: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

o   2130: PCRS, DLH, and UCATS will have post-landing access for Cal. Gas Shutoff

o   Zone-25 and Z-14 (R2) to be removed temporarily after weighing for this access

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.