ATTREX 01/08/13 Daily Schedule

1/8 Accompishments:
NOAA O3, UCATS and HU/PCRS pump box re-installed
Software uploaded to Link Module and NASDAT
Iridium checks accomplished with minor glitches
Aircraft Ku system locked onto AMC16 satellite; ground station not able to do so yet

1/9 Plans:
Roll aircraft out at 08:00 to continue effort to get ground station locked onto AMC16
We'll get a call in the hangar when they want instrument team representatives to report to the GHOC
If successful early enough continue to the pre Combined System Test (CST)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.