ATTREX 02/10/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.

Accomplishments:
  • GHOST mechanical installation completed (see pic)
  • AIITS Pod structural dynamics (“Ping”) test completed (see pic)
Concerns / Watch List:
  • AIITS replacement Diode Laser - delivery expected tomorrow.
  • Cannot locate 2nd MMS EIP Harness. OA may need to fabricate a replacement.
  • NGC Shear/Bending analysis – holding for new NGC analysis using updated model.
Upcoming Schedule:
  • Tomorrow, Wednesday:
    • CAST/ATTREX Leads Telecom at 0800 PST
    • Hawkeye Harness end-to-end checks (Zone-3 and Pod)
    • MMS EIP Harness review (Zone-7)
    • GHOST ATR Ping Setup and Test
    • GHOST Harness installation (after Ping Test, time permitting)
  • Thursday:
    • Weight & Balance by NGC Engr.
    • Data-IT Testing in Hangar (time permitting)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.