ATTREX 02/05/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Installation is 2 days behind schedule… currently the only instrument not mounted.

Accomplishments:
  • Cabin Pressurization test completed
  • Avionics tie-up of harnesses ongoing
  • AIITS Pod mounted on the wing, preloads almost completed
  • CAST/ATTREX Leads Status/Flight Planning telecom held
  • Final pre-installation work on the GHOST Pallet continuing
Concerns / Watch List:
  • AIITS Diode Laser replacement arrival by early next week.
  • Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
  • GHOST Pallet installation is behind schedule – mounting on aircraft to begin tomorrow
  • NGC Shear/Bending analysis - Meeting at NGC tomorrow to discuss status
Upcoming Schedule:
  • Tomorrow, Friday:
    • Finish AIITS Pod load-cell preloads
    • Continue Avionics tie-up of harnesses
    • GHOST Pallet installation
  • Saturday: Finish GHOST Installation

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.