ATTREX 02/04/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Z-25 installation is behind schedule due to a delay in pallet prep, however the pallet is expected tomorrow.

Accomplishments:
  • All Instruments have passed SIL Bench Testing.
  • AIITS Pod completes Environmental Testing
  • MMS, MPT, Hawkeye, NWV, O3, and GWAS are mechanically installed.
  • AIITS fiber installed – Cabin Pres. Test Thursday AM
Concerns / Watch List:
  • AIITS Diode Laser replacement arrival by early next week.
  • Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
  • GHOST Pallet installation is behind schedule – expected to begin tomorrow
  • NGC Shear/Bending analysis - Meeting at NGC on Friday to discuss status
Upcoming Schedule:
  • Tomorrow, Thursday:
    • 0800 CAST/ATTREX Proj. Lead Telecom
    • Cabin Pressurization Test
    • Continue Avionics tie-up of harnesses
    • AIITS Pod Installation
    • GHOST Pallet installation
  • Friday / Saturday:
    • Finish GHOST Installation
    • Aircraft Wt. & Balance (day/time TBD)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.