ATTREX 02/04/14 Daily Schedule

ATTREX  GH Overview:

- Instrument & Aircraft Pre-flight tomorrow for a planned Thursday flight, 0700 Takeoff.

 

The Schedule for tomorrow is:

- 0730 - 1030: Outdoor testing of Ku System

- 1000: T-1 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 1100 – 1300: Instrument Preflight

  o Instrument Team hands-off at 1300

- 1300 – 1600: Aircraft Preflight

 

The Schedule for Thursday is:

- 0000 – 0300 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0300

- 0500: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0545: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0600: Engine Start

- 0700 (2100 Z, Wed): Take-off for a planned 14-hr flight

- 1900 (0900 Z, Thurs): Est. Landing time

 

The Current Plan for Friday is for Aircraft and Instrument Post-flight:

- 0600 - ~1100: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1100 - 1300: Access to instruments with aircraft power and Data-IT support

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.