ATTREX 01/22/14 Daily Schedule

GH Overview:
- Rain, Rain… (Deluge, deluge) go away.
- Pics to prove the point.
 
Today’s Accomplishments:
- Final activity by Instrument Teams prior to preflight for first Science Flight
- Some teams have completed their pre-flight activity.
- Announcement of a 1-day delay in the Science Flt.
 
The Plan for tomorrow (Thursday) is:
- 0800 – 0945: Req’d Engine wash by Crew
- 1000 – 1300: Instrument Team Pre-flight access with Power.
  o Please start at 1000 – hands off at 1300.
- 1300 – 1600: Aircraft Preflight by GH Crew
- 1400: Science Team Meeting
- (TBA): T-1 Briefing for First Science Flight
 
The Current Schedule for Flight Day (Friday) is:
- 2300 – 0200:  Special Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.
  o Instrument Team hands-off at 0200
- 0400: T-0 Briefing with GH Team & Science Leads
- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew
- 0500: Engine Start
- 0600: Take-off
- 2000: Estimated Landing time (14-hr flight)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.