ATTREX 01/13/14 Daily Schedule

ATTREX  GH Overview:
  • ATTREX Instruments Ready for final pre-flight procedures.
  • A/C To PMOF (Guam) Comm Testing Guam successfully accomplished on Jan 9th.
Today's Accomplishments:
  • ATTREX air cargo picked up. ETA to Guam: Jan 16th and at AAFB: Jan 17th.
  • Ongoing Comm Testing: A/C To GMOF (Guam). Testing to continue on Tuesday, Jan 10th.
Plans for Tuesday, Jan 14 (@ DFRC):
  • 0900 – 1130 Instrument teams have power and aircraft access in the hangar.
  • 1200 – 1700 Aircraft outdoors for continuation of comm testing with GHMOF in Guam.
    • For limited access while the plane is outdoors, please coordinate with Jhony Zavaleta.
 
Plans for Wednesday, Jan 15th (@ DFRC): (Schedule will be revised as needed)
  • 1100  A/C Power On. Instrument teams have aircraft access.
  • 1400  Hands off / Power Off
  • 1500  Aircraft Roll Out
  • 1645  Instrument teams to GHOC
    • (User packets will go straight to Guam. Presence in GHOC desired for any questions/troubleshooting by IT prior to launch.)
  • 1700  Engine Starts
  • 1800  Take Off
TRANSIT FLIGHT PLAN:
  • TAKE OFF: from DFRC on Wednesday, Jan 15th, 1800 PST / Thursday, 16th, 1200 ChST (Guam)
    • PMOF Staffing in Guam at 1045 for all Instrument Teams
  • LANDING:  in Guam on Friday, Jan 17th, 0800 CHST / Thursday, Jan 16th 1400 PST

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.