1/12 Accomplishments:
49ers completely dispatch The Pack
MMS network interface problem turned out to be a bad ethernet cable; it was changed and the system works fine
GWAS fixed a noisy manifold pressure sensor
HU/PCRS continued system calibration work
DLH performed high altitude pressure control system work
1/13 Plans:
Off aircraft instrument system work
The current schedule calls for Combined System Test on Monday, preflight on Tuesday for a range flight on Wednesday, preflight Thursday a.m. for a p.m. take off for a science flight