ATTREX 01/09/14 Daily Schedule

ATTREX GH Overview:
  • Instrument Team’s continue to return to DFRC and work on their instruments.
Today’s Accomplishments:
  • GH Team has successful DFRC Tech Brief for ATTREX Mission.
  • ATTREX Science Team Meeting
  • ESPO continued to prep the LD3’s for loading with Science-related equipment for shipment to Guam.

The Plan for the Tomorrow (Thursday at DFRC) DFRC Comm’s testing Aircraft to PMOF:

  • Aircraft Crew shifted to support late day testing with Guam.
  • Instrument Team’s may have access prior to aircraft going outdoors if needed:
    • 0900 – 1130 access in Hangar.
    • Please coordinate your needs with Dave F. and/or Jhony Z.
  • Aircraft outdoors 1200 – 1700 PST (0600 – 1100 Guam) for Comm’s testing with PMOF in Guam
    • Instruments may be supported in the GHOC – see Caitlin if possible.

Friday is a contingency outdoor Satcom day as needed for more PMOF Testing with the aircraft.

There are NO Planned activities in the GHOC Hangar for the period Saturday - Sunday:

  • Aircraft Crew will not be available. No aircraft access of any kind.
  • If Instrument Teams want to work in the Payload Cage over the weekend please coordinate with Dave F. or Jhony Z.

The Plan for the period Monday – Tuesday is primarily for outdoor Aircraft to GHMOF Satcom Testing:

  • Aircraft Crew shifted to support late day testing with Guam.
  • Instrument Team’s may have access prior to aircraft going outdoors if needed:
    • 0900 – 1130 access in Hangar.
    • Please coordinate your needs with Dave F. and/or Jhony Z.
  • Aircraft outdoors 1200 – 1700 PST (0600 – 1100 Guam) for Comm’s testing with GHMOF in Guam
 (Continued PMOF Testing from this week will be supported as needed)
    • Monday is scheduled, Tuesday is margin, as needed by GH/Avionics Team
Transit / Science Flight Plan:
  • Transit/Science (planned for 20 hour) Flight of AV-6 to Guam is currently scheduled for:
    • Take-off from DFRC on Wednesday 1700 DFRC (Thursday 1100 Guam)
      • PMOF Staffing in Guam at 0945 for all Instrument Teams
    • Scheduled Landing in Guam on Friday 0700 (Thursday 1300 DFRC)
  • Reminder regarding Support:
    • Instrument Preflight in GH Hangar will start on Wednesday morning
    • All instruments Teams should plan to have at least one person at DFRC prior to the Transit Flight to preflight their instrument

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.