Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

Associated content: 

GHOST Environmental Prep

Date: 
Thursday, January 8, 2015 (All day) - Friday, January 9, 2015 (All day)

Hawkeye SIL Bench Tests and A/C Installation Begins

Date: 
Monday, December 1, 2014 (All day) - Friday, December 5, 2014 (All day)

AIITS Installation Prep

Date: 
Thursday, December 4, 2014 (All day) - Friday, December 5, 2014 (All day)

AIITS Environmental Testing

Date: 
Monday, November 24, 2014 (All day) - Wednesday, November 26, 2014 (All day)

GWAS SIL Bench and A/C Installation

Date: 
Monday, January 12, 2015 (All day) - Friday, January 16, 2015 (All day)

GWAS Personnel Arrive

Date: 
Sunday, January 11, 2015 (All day)

GHOST unpack, SIL Bench Tests

Date: 
Monday, January 5, 2015 (All day) - Wednesday, January 7, 2015 (All day)

AIITS, Hawkeye Personnel Depart

Date: 
Saturday, December 13, 2014 (All day)

AIITS A/C Installation

Date: 
Monday, December 8, 2014 (All day) - Friday, December 12, 2014 (All day)

AIITS Enviro. Prep

Date: 
Friday, November 21, 2014 (All day)