Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Sun | Mon | Tue | Wed | Thu | Fri | Sat |
---|---|---|---|---|---|---|
26 |
27 |
28 |
29 |
30 |
||
«
Boeing Atomspheric Sensor
2011-06-02 - 2011-06-30
|
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
|||||
«
AVIRIS
2011-06-23 - 2011-07-10
»
|
||||||
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Maintenance / Engineering Mod #3
2011-03-01 - 2011-06-27
|
Halo-Red Payload Integration & Test
2011-06-28 - 2011-07-12
»
|
|||||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
Pollock
2011-06-25 - 2011-06-26
|
|
|
BAS Download
2011-06-29 - 2011-06-30
|
AFRL
2011-07-01 - 2011-07-31
»
|
||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
CARVE Mission
2011-04-04 - 2011-07-01
|
|
|||||
«
Oil Spill & Hispaniola Deployment
2011-06-22 - 2011-06-30
|
Flight Testing
2011-07-01 - 2011-07-31
»
|
|||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
Nadir Port Modification
2011-04-01 - 2011-06-30
|
|
|
||||
«
APCS
2011-04-04 - 2011-07-01
|
|
|||||
«
G-LiHT & EPA Joint Sensors
2011-06-20 - 2011-07-01
|
|
|||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
»
|
||||||
«
Reimbursable mods
2011-05-16 - 2011-07-29
»
|
||||||
«
Upload DISCOVER-AQ
2011-05-30 - 2011-07-01
|
|
|||||
«
DISCOVER-AQ Upload
2011-06-06 - 2011-07-01
|
|
|||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
|
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
|||||
|
|
|||||
«
AVIRIS
2011-06-23 - 2011-07-10
»
|
||||||
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Halo-Red Payload Integration & Test
2011-06-28 - 2011-07-12
»
|
||||||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
||||||
«
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
||||||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
AFRL
2011-07-01 - 2011-07-31
»
|
||||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
»
|
||||||
«
Reimbursable mods
2011-05-16 - 2011-07-29
»
|
||||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
«
Flight Testing
2011-07-01 - 2011-07-31
»
|
||||||
|
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
|||||
AMIGA-Carb using G-LiHT
2011-07-04 - 2011-07-29
»
|
||||||
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
|
SWEEPSAR Upload
2011-07-05 - 2011-07-07
|
SWEEPSAR
2011-07-08 - 2011-07-09
|
||||
|
|
|
|
|||
«
AVIRIS
2011-06-23 - 2011-07-10
|
|
Diner
2011-07-12 - 2011-07-13
|
|
|
|
|
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Halo-Red Payload Integration & Test
2011-06-28 - 2011-07-12
|
|
|
|
|
||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
||||||
«
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
||||||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
AFRL
2011-07-01 - 2011-07-31
»
|
||||||
«
AMIGA-Carb using G-LiHT
2011-07-04 - 2011-07-29
»
|
||||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
Reimbursable mods
2011-05-16 - 2011-07-29
»
|
||||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
«
Flight Testing
2011-07-01 - 2011-07-31
»
|
||||||
|
|
AirMSPI/AVIRIS/RSP
2011-07-12 - 2011-07-15
|
|
|||
ASCENDSII Instrument Upload
2011-07-11 - 2011-07-22
»
|
||||||
HS3 Integration
2011-07-11 - 2011-08-31
»
|
||||||
|
|
|
|
|||
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
||||||
«
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
||||||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
ASCENDSII Instrument Upload
2011-07-11 - 2011-07-22
|
|
|||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
AFRL
2011-07-01 - 2011-07-31
»
|
||||||
«
AMIGA-Carb using G-LiHT
2011-07-04 - 2011-07-29
»
|
||||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
Reimbursable mods
2011-05-16 - 2011-07-29
»
|
||||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
«
Flight Testing
2011-07-01 - 2011-07-31
»
|
||||||
«
HS3 Integration
2011-07-11 - 2011-08-31
»
|
||||||
|
AVIRIS
2011-07-18 - 2011-07-20
|
|
|
|||
|
||||||
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
||||||
«
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
||||||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
AFRL
2011-07-01 - 2011-07-31
»
|
||||||
«
AMIGA-Carb using G-LiHT
2011-07-04 - 2011-07-29
|
|
|||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
»
|
||||||
«
Reimbursable mods
2011-05-16 - 2011-07-29
|
|
|||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
«
Flight Testing
2011-07-01 - 2011-07-31
»
|
||||||
«
HS3 Integration
2011-07-11 - 2011-08-31
»
|
||||||
|
ASCENDSII Instrument Development Flights
2011-07-25 - 2011-08-06
»
|
|||||
|
JSC DEPLOYMENT (MASTER, AVIRIS)
2011-07-26 - 2011-08-18
»
|
|||||
|
Preparing for Alaska Deployment
2011-07-28 - 2011-07-29
|
|
||||
|
|
|||||
1 |
2 |
3 |
4 |
5 |
6 |
|
«
Reimbursable Flight Missions
2011-05-02 - 2011-11-14
»
|
||||||
«
Autopilot Modifications
2011-03-28 - 2011-08-13
»
|
||||||
«
809 Phase Inspection
2011-07-01 - 2012-05-25
»
|
||||||
«
G-LiHT & AMIGA-Carb
2011-06-30 - 2011-10-31
»
|
||||||
«
N928 DEPLOYMENT
2011-04-04 - 2011-09-10
»
|
||||||
«
JSC DEPLOYMENT (MASTER, AVIRIS)
2011-07-26 - 2011-08-18
»
|
||||||
«
NADIR port installation
2011-03-07 - 2011-09-09
»
|
||||||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
|
||||||
«
Non-flyable storage
2011-01-01 - 2011-12-31
»
|
||||||
«
AFRL
2011-07-01 - 2011-07-31
|
CARVE Mission
2011-08-01 - 2011-10-31
»
|
|||||
«
ASCENDSII Instrument Development Flights
2011-07-25 - 2011-08-06
|
||||||
«
AVIRIS Mission
2011-04-04 - 2011-07-31
|
Alaska Deployment
2011-08-01 - 2011-08-04
|
|
|
|||
«
DISCOVER-AQ
2011-07-04 - 2011-08-06
|
||||||
«
DEVOTE Mods
2011-06-20 - 2011-08-31
»
|
||||||
«
Flight Testing
2011-07-01 - 2011-07-31
|
|
|
|
|
|
|
«
HS3 Integration
2011-07-11 - 2011-08-31
»
|
||||||
|
|
|
|
|
|
|