IMPACTS 02/08/20 Mission Daily Schedule

Plan of the day for Sunday, February 09

For the long-term (forecasting and science) tentative plans, please refer to the Daily Science plan.

IMPACTS General

Sunday, Feb 09
09:00-10:00: Daily Briefing (Wallops W162; Webex/Telecon)

Monday, Feb 10
09:00-10:00: Daily Briefing (Wallops W162; Webex/Telecon)

IMPACTS P-3 - Wallops
Saturday, Feb 09
Hard Down Day

Monday, Feb 10
0800 - 1630 A/C Access

IMPACTS ER-2 - Hunter
Sunday, Feb 09
Hard Down Day

Monday, Feb 10
0700 - 1530 A/C Access

ESPO Crew on Deck
Wallops: Dan Chirica  (650 318-8257), Caitlin Murphy  (650-680-7732)
Hunter:   Bernie Luna (650 417-8810)
IMPACTS Webex telecon : +844 467 4685  code: 804464#

Saturday, Feb 08
0730 - 1500 A/C Access

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.