ATom

Synonyms
Atmospheric Tomography Mission
ATom 03/28/18 Mission Daily Schedule
Wednesday, March 28 Accomplishments
  • WAS racks on aircraft
  • GT-CIMS powered on aircraft, running lines to cylinder rack
  • NOAA CIMS and CIT-CIMS finishing up integration, testing on aircraft
  • MMS working on software
  • PANTHER/UCATS running instruments in lab
Thursday, March 29 Plan
  • 06:00 - 17:30: A/C Access
  • 13:00: Daily brief in lab
  • 13:30: Egress training
  • WAS window plate and inlet to be installed
Other notes:
  • Please sign in on arrival to the instr
ATom 03/27/18 Mission Daily Schedule
Tuesday, March 27 Accomplishments
  • CIT-CIMS pump installed and instrument powered. Team is finishing up integration and will begin cryo servicing either this afternoon or tomorrow.
  • NOAA CIMS and GT-CIMS racks on aircraft
  • MMS working on software
  • PANTHER/UCATS running instruments in lab
Wednesday, March 28 Plan
  • 06:00 - 17:30: A/C Access
  • CIT-CIMS, NOAA CIMS, and GT-CIMS continue integration
  • WAS installation
ATom 03/26/18 Mission Daily Schedule
Monday, March 26 Accomplishments
  • CIT-CIMS rack installed and cabled
  • NOAA CIMS cylinders loaded onto aircraft, exhaust line and inlet installed, rack powered and checked out in lab
  • GT-CIMS cylinders loaded onto aircraft, prepping rack in lab
  • MMS troubleshooting software
Tuesday, March 27 Plan
  • 06:00 - 17:30: A/C Access
  • CIT-CIMS pump installation
  • NOAA CIMS rack upload
ATom 03/22/18 Mission Daily Schedule
Thursday, 3/22 Accomplishments
  • AO2/Medusa continued optimizing
  • CAPS team departs
  • GT-CIMS power up in lab
  • HR-AMS calibrations and software
  • ISAF completed installation
  • Sea shipment departed for Christchurch
  • Cylinder shipment departed for Anchorage, Kona and Lajes
Friday, 3/23 Plans
  • AO2/Medusa team departs
  • GT-CIMS lab work
  • HR-AMS team departs
  • ISAF team departs
ATom 03/21/18 Mission Daily Schedule

Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow

Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.