Thursday, March 29 Accomplishments
- GT-CIMS, NOAA CIMS, and CIT-CIMS installed and power checked
- PANTHER/UCATS running instruments in lab
Friday, March 30 Plan
- WAS to continue integration
- 06:00 - 09:00: A/C outside for testing.
Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow
Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF
Tuesday, 3/20 Accomplishments
AO2/Medusa finished installed plumbing and powered up
CAPS cross computer calibrations and systems checks
GT-CIMS staged shipping material and began to unpack
HR-AMS installed and conducted power checks and alignment
ISAF completed mechanical installation and began cabling
Shipment preparations
Monday, 3/19 Accomplishments
AO2/Medusa, ISAF and HR-AMS arrived
AO2/Medusa installed and powered on
ISAF installed
HR-AMS calibrating in lab
Tuesday, 3/20 Plans
06:00-17:30 A/C access
HR-AMS planning to install
Monday, 3/19 Plan
07:00 Badge office opens (for those with expired badges)
06:00-18:00 A/C access
CAPS installation continues
AO2/Medusa, HR-AMS, ISAF teams begin installations
Friday, 3/16 Accomplishments
All first round instruments installed
No NOyO3 issues
CAPS installation complete
Monday, 19 Plan
ISAF, AO2/Medusa & HR-AMS begin installations
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.