Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

IMPACTS 02/26/23 Mission Daily Schedule

Plan of the Day for Sunday, February 26th
All times are in Eastern Standard Time (EST) 
 
All - 0900 Daily Weather Briefing 
 
WALLOPS 
 
Sunday 26 February: Hard Down Day
No aircraft access 
 
Monday 27 February: No Fly, Work Day 
0830 – 1600: Aircraft access and power for instrument teams
 
DOBBINS 
 
Sunday 26 February: Calibration Flight, ER-2
0600: Hands On
0700: Hands Off / Tow / Crew Brief – Hangar 5 Science Room 1026 and MS Teams
1000: Take Off
 ~1430: Landing
 ~1530: Debrief – Hangar 5 Science Room 1026 and MS Teams
 
Monday 27 February: No Fly Work Day
~ 0800 – 1400: Aircraft access and power for instrument teams
(Note: Subject to change based on Tuesday schedule)
 
General announcements
REMINDER: Foreign Nationals must be escorted when accessing WFF after hours and on national holidays (hours outside 0600 - 1800). Coordinate with Kelly or ESPO if you need an escort.
 
Current health guidelines call for:
Wallops – No regulations
Dobbins – No regulations
 
Project Swag:  https://www.cafepress.com/IMPACTSShop
Field catalog with the tentative weekly schedule: http://catalog.eol.ucar.edu/impacts_2023
Project picture gallery (please contribute by uploading your project pictures).
Please complete the check-in form upon arrival at Wallops or Dobbins.
Science flights project totals ER-2 (11), P-3 (1)