Daily Schedule

Date: Feb 13, 2025

 

Location: NASA JSC

 

*****Due to the potential extension of the campaign (final last flight date of the 22nd, and NOAA truck on the 24th) don’t wait to extend your hotel reservation. You can adjust your reservation by calling 832-328-0450, by emailing Brittany.Hipolito@marriott.com or in person at the front desk.

 

Daily Integration Schedule

  • Maintenance: 0630 - 1715
  • Engineering:  0800 - 1600
  • Aircraft Access: TBD, but be ready by 0815 in case they are ready to go 
    • 0800 - 1600 Support of FN escort and door access
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Due to delays associated with aircraft repairs, the flight has been rescheduled for Friday, Feb 14th 1pm. 
  • The next flight opportunity after Friday is Sunday, Feb 16th with a hard down day on Monday, Feb 17th. 

Notes:

  • Power was restored on the aircraft, but unfortunately a small fuel leak was discovered during the repair. 
  • Friendly reminder to please coordinate with maintenance or engineering before you approach the aircraft

SABRE Plan of the Day

Date: Feb 11, 2025

Location: NASA JSC

Daily Integration Schedule

  • 0800 - 1600 Support of FN escort and door access
  • 0815: Morning Stand Up (1 payload rep for each team)
  • 1500: Afternoon Tag Up  (1 payload rep for each team)
  • Troubleshooting the electrical system so, no aircraft access unless there is progress
  • Updates will be posted on the group chat
  • Engineering will not be available, unless we the power issue is resolved

Planned Activities:

  • Earliest flight opportunity Thursday, weather permitting


 

Date: Feb 10, 2025

Location: NASA JSC

Daily Integration Schedule

  • 0800 - 1600 Support of FN escort and door access
  • 0815: Morning Stand Up (1 payload rep for each team)
  • 1500: Afternoon Tag Up  (1 payload rep for each team)
  • Troubleshooting the electrical system so, no aircraft access unless there is progress
  • Updates will be posted on the group chat
  • Engineering will not be available, unless we the power issue is resolved

Planned Activities:

  • Earliest flight opportunity Thursday, weather permitting
  • Thursday is the next flight opportunity

SABRE Plan of the Day

Date: Feb 9, 2025 

Location: NASA JSC

Daily Integration Schedule

  • 0800 - 1600 Support of FN escort and door access
  • Hard Down Day (no aircraft access)
  • Updates will be posted on the group chat

Planned Activities:

  • Earliest flight opportunity Tuesday, weather permitting
  • Thursday is the next flight opportunity


 

SABRE Plan of the Day

Date: Feb 8, 2025

Location: NASA JSC

Daily Integration Schedule

  • 0800 - 1600 Support of FN escort and door access
  • Troubleshooting the electrical system so, no aircraft access unless there is progress
  • Updates will be posted on the group chat
  • Engineering will not be available, unless we the power issue is resolved

Planned Activities:

  • Sunday, Feb 9, is a Hard Down Day for the WB-57 crew
  • Soonest flight opportunity Tuesday, weather permitting
  • Thursday is the next flight opportunity

Notes:

  • Jhony Zavaleta is replacing Dan

SABRE Plan of the Day 

Date: Feb 7, 2025

Location: NASA JSC

Daily Integration Schedule

  • Maintenance: 0630 - 1530
  • Engineering:  0800 - 1600 (support for FN escort and doors access) 
  • Aircraft Access: 0800 - 1500 aircraft access
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1200: Deadline for requesting extended Engineering or Maintenance support
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Dress rehearsal
  • Power on Aircraft checks 

SABRE Plan of the Day

Date: Feb 6, 2025

Location: NASA JSC

Daily Integration Schedule

  • Maintenance: 0630 - 1530
  • Engineering:  0800 - 1600 (support for FN escort and doors access) 
  • Aircraft Access: 0820 - 1500 aircraft access
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1200: Deadline for requesting extended Engineering or Maintenance support
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Power on Aircraft checks 
  • Pallet inspections
  • Complete mechanical/electrical inspections as the payloads get fully assembled
  • Continue weighing payloads 

SABRE Plan of the Day

Date: Feb 5, 2025

Location: NASA JSC

Daily Integration Schedule

  • Maintenance: 0630 - 1530
  • Engineering:  0800 - 1600 (support for FN escort and doors access) 
  • Aircraft Access: 01300 - 1530 potential aircraft access
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1200: Deadline for requesting extended Engineering or Maintenance support
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Power on aircraft checks 
  • Pallet inspections
  • Complete mechanical/electrical inspections as the payloads get fully assembled
  • Continue weighing payloads 


 

SABRE Plan of the Day

Date: Feb 4, 2025

Location: NASA JSC

Daily Integration Schedule

  • Maintenance: 0630 - 1530
  • Engineering:  0800 - 1600 (support for FN escort and doors access) 
  • Aircraft Access: 01300 - 1530 potential aircraft access
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1200: Deadline for requesting extended Engineering or Maintenance support
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Pallet inspections
  • Complete mechanical/electrical inspections as the payloads get fully assembled
  • Continue weighing payloads

SABRE Plan of the Day

Date: Feb 3, 2025

Location: NASA JSC

Daily Integration Schedule

  • Maintenance: 0630 - 1715
  • Engineering:  0800 - 1600 (support for FN escort and doors access) 
  • Aircraft Access: 0800 – 1530 likely no AC access tomorrow, there is a flight planned for the morning
  • Daily Flow
    • 0815: Morning Stand Up (1 payload rep for each team)
    • 1200: Deadline for requesting extended Engineering or Maintenance support
    • 1500: Afternoon Tag Up  (1 payload rep for each team)

Planned Activities:

  • Pallet inspections
  • Complete mechanical/electrical inspections as the payloads get fully assembled
  • Continue weighing payloads 
  • TRR (test readiness review) scheduled at 1330.