SABRE Plan of the Day
Date: Feb 23, 2025
Location: NASA JSC
Daily Integration Schedule
- Pack Up Day
- 0800 - 1600 Support of FN escort and door access
SABRE Plan of the Day
Date: Feb 23, 2025
Location: NASA JSC
Daily Integration Schedule
NASA WB-57 Schedule
0600 MX Show / Pre-flight
0700 Payload Access: Instruments must be ready to go by 0650. (Teams can have access to
aircraft earlier once WB MX lead advises, do not approach until then)
0800 Payload Access Complete
0815 Flight Plan Review (Science Leads and Aircrew)
0830 Mission Brief - Go/No-Go (Bldg. 994)
0830 Tow / Refuel (20,000 lbs)
0930 Aircrew Suit Up
0945 Aircrew Aircraft Preflight
1015 Aircrew Cockpit Integration
1035 Engine Start
1055 Taxi
1100 Take Off
1600 Land
1630 Debrief (Bldg. 994)
1630 Payload Access (once maintenance post flight is done, do not approach without notification from WB team)
1800 Day Complete ‘ish
Planned Activities:
Notes:
SABRE Plan of the Day
Date: Feb 21, 2025
Location: NASA JSC
*****Due to the potential extension of the campaign (final last flight date of the 22nd, and NOAA truck on the 24th) don’t wait to extend your hotel reservation. You can adjust your reservation by calling 832-328-0450, by emailing Brittany.Hipolito@marriott.com or in person at the front desk.
Daily Integration Schedule
Planned Activities:
SABRE Plan of the Day Feb 20, 2025 TF #4
Location: NASA JSC
NASA WB-57 Schedule
0600 MX Show / Pre-flight
0700 Payload Access: Instruments must be ready to go by 0650. (Teams can have access to
aircraft earlier once WB MX lead advises, do not approach until then)
0800 Payload Access Complete
0815 Flight Plan Review (Science Leads and Aircrew)
0830 Mission Brief - Go/No-Go (Bldg. 994)
0830 Tow / Refuel (20,000 lbs)
0930 Aircrew Suit Up
0945 Aircrew Aircraft Preflight
1015 Aircrew Cockpit Integration
1035 Engine Start
1055 Taxi
1100 Take Off
1600 Land
1630 Debrief (Bldg. 994)
1630 Payload Access (once maintenance post flight is done, do not approach without notification from WB team)
1800 Day Complete ‘ish
Planned Activities:
SABRE Plan of the Day
Date: Feb 19, 2025
Location: NASA JSC
Daily Integration Schedule
Planned Activities:
SABRE Plan of the Day Feb 18, 2025 TF #3
Location: NASA JSC
NASA WB-57 Schedule
0500 MX Show / Pre-flight
0600 Payload Access: Instruments must be ready to go by 0550. (Teams can have access to aircraft earlier once WB MX lead advises, do not approach until then)
0700 Payload Access Complete
0715 Flight Plan Review (Science Leads and Aircrew)
0730 Mission Brief - Go/No-Go (Bldg. 994)
0730 Tow / Refuel (20,000 lbs.)
0830 Aircrew Suit Up
0845 Aircrew Aircraft Preflight
0915 Aircrew Cockpit Integration
0935 Engine Start
0955 Taxi
1000 Take Off
1500 Land
1530 Debrief (Bldg. 994)
1530 Payload Access (Once maintenance post flight is done, do not approach without notification from WB team)
1700 Day Complete ‘ish
SABRE Plan of the Day
Planned Activities:
SABRE Plan of the Day, JSC, 15 Feb 2025
Notes:
POD
SABRE Plan of the Day: NASA WB-57, Flight Test #1 (JSC)
0700 MX Show / Pre-flight
0800 Payload Access: Instruments must be ready to go by 0750. (Teams can have access to aircraft earlier once WB MX lead advises the PI.)
0945 Flight Plan Review (Science Leads and Aircrew)
1000 Payload Access Complete
1000 Mission Brief - Go/No-Go (Bldg. 994)
1030 Tow / Refuel (20,000 lbs)
1130 Aircrew Suit Up
1145 Aircrew Aircraft Preflight
1215 Aircrew Cockpit Integration
1235 Engine Start
1255 Taxi
1300 Take Off
1600 Land
1630 Debrief (Bldg. 994)
1630 Payload Access
1900 Day Complete ‘ish
Looking Ahead
Saturday, Feb 15: Aircraft Access
Sunday, Feb 16: Flight day
Monday, Feb 17: Hard Down Day