FIREX-AQ

Synonyms
FIREChem
FIREX-AQ 06/07/19 Mission Daily Schedule

Friday, 6/7, Accomplishments:
Instrument integration
MASTER loaded in aft cargo pit
A/C O2 system checks

Saturday, 6/8, Plans:
08:00 - 09:30    A/C Access
09:30 - 11:00 (an estimate of completion time) A/C O2 system work, no A/C access
After the completion of the O2 system work there will be A/C access until 15:30

Send pressure system schematics to Richard Wong
Send heater system schematics to Paul Martinez/Brennan Wehr
FIREX-AQ 06/06/19 Mission Daily Schedule

Thursday, 6/6, Accomplishments:
OPALS team performed probe fit check
ACES/IWAS rack installed
TOGA continued working on sampling lines between inlet and instrument
DIAL team made good progress
mini-DOAS team performed in-lab calibrations
NO LIF instrument removed from rack; to be reinstalled on the 18th

Friday, 6/7, Plans:
06:00 A/C Access
MASTER to load aft pit
Instrument integration tasks
13:00 Lab meeting
17:30 A/C access ends

FIREX-AQ 06/05/19 Mission Daily Schedule

Wednesday, 6/5, Accomplishments:
OPALS team performed in lab installation prep
mini DOAS team performed in lab calibrations
ACES and IWAS testing in lab, waiting for the install window
TOGA installed
ISAF/ROZE/CANOE and SO2/NO-LIF installed
CIT-CIMS rack and pump plate installed
DIAL completed nadir alignments

Thursday, 6/6, Plans:
06:00 A/C Access
IWAS/ACES install
Instrument installations and integration
13:00 Lab meeting
17:30 A/C access ends

FIREX-AQ 06/04/19 Mission Daily Schedule

Tuesday, 6/4, Accomplishments:
UCLA WAS kicked off project
UCI WAS installed
IWAS rack satisfied over-turning moment on 2nd attempt
UCI WAS, TOGA and MMS installed
NOAA LGR/PTR-ToF-MS rack on A/C
ISAF, SO2 (NO-LIF) rack prepped for install
CIT-CIMS rack prepped for install 
mini-DOAS prepped for install (rack already on A/C)

Wednesday, 6/5, Plans:
06:00 A/C Access
Instrument installations and integration
13:00 Lab meeting
17:30 A/C access ends

FIREX-AQ 05/31/19 Mission Daily Schedule

Friday, 5/31 Accomplishments:
SP2 completed integration
CAMS, DLH/DACOM, HR-AMS2, GT-CIMS and PTR-MS continued A/C integration

Saturday, 6/1 Plans:
07:00 A/C access
CARE to receive new circuit board and begin replacement/checkout
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez
FIREX-AQ 05/30/19 Mission Daily Schedule

Thursday, 5/30 Accomplishments:
CAMS, CARE, DLH/DACOM, Iodide CIMS, LARGE, PTR-MS and SP2 continued on A/C integration
HR-AMS and GT-CIMS installed

Friday, 5/31 Plans:
07:00 A/C access
On A/C Integration work to continue
13:00 Lab meeting
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez
FIREX-AQ 05/29/19 Mission Daily Schedule

Wednesday, 5/29 Accomplishments:
CARE, DLH/DACOM and LARGE continued on A/C integration work 
CAMS, Iodide CIMS and SP2 racks deftly installed
HR-AMS and GT-CIMS continued in-lab preparation for installation

Thursday, 5/30 Plans:
06:00 A/C access
Installation/integration work to continue
HR-AMS to install in the a.m.
GT-CIMS to install in the p.m.
13:00 Lab meeting
17:30 A/C access ends