Tuesday, 6/4, Accomplishments:
UCLA WAS kicked off project
UCI WAS installed
IWAS rack satisfied over-turning moment on 2nd attempt
UCI WAS, TOGA and MMS installed
NOAA LGR/PTR-ToF-MS rack on A/C
ISAF, SO2 (NO-LIF) rack prepped for install
CIT-CIMS rack prepped for install
mini-DOAS prepped for install (rack already on A/C)
Wednesday, 6/5, Plans:
06:00 A/C Access
Instrument installations and integration
13:00 Lab meeting
17:30 A/C access ends