FIREX-AQ 06/15/19 Mission Daily Schedule
Saturday, 6/15 Accomplishments:
  • A/C was outside and remains outside
  • CIT-CIMS, DACOM, LGR CO & LARGE performed maintenance, software checks, plumbing
  • DIAL calibrated
  • MMS/Data performed GPS checks
  • mini DOAS ran test scans and checked communications

Sunday, 6/16, Plans:
Lab access only, LN2 servicing

Monday, 6/17, Plans:
Plane outside if DIAL needs more calibration time: tbd
0600 A/C Access, with O2 work given priority
1730 Access ends

FIREX-AQ 06/13/19 Mission Daily Schedule
Thursday, 6/13, Accomplishments:
  • CIT-CIMS, LINeph & Master performed instrument checks, integration/software refinements, calibration, maintenance
  • DIAL prepped for calibration
  • The neph plate was installed (LARGE nephelometers, Laser Imaging neph)
  • TOGA was successfully tuned
  • DACOM completed some plumbing installs, power checks, software mods

Friday, 6/14, Plans:
Inside
0700 A/C access concurrent with O2 work. Possible intermittent power and clearing the A/C of science staff

FIREX-AQ 06/12/19 Mission Daily Schedule
Wednesday, 6/12, Accomplishments:
  • LARGE, TOGA, Mini-DOAS, CIT-CIMS, LINeph & Master performed instrument checks, integration refinements, maintenance around the O2 system work
  • DIAL prepped for calibration

Thursday, 6/13, Plans:
Still inside
0600 A/C access – continuous power until 1300.
**Please show at 0600 if you requested multiple hours of continuous power.
**O2 work concurrent; could be crowded
**After 1300, possible power interruption and clearing the A/C for O2 system work

FIREX-AQ 06/11/19 Mission Daily Schedule

Tuesday, 6/11, Accomplishments:
LARGE, TOGA, Mini-DOAS, CIT CIMS, MMS, LINeph & Master performed instrument checks, integration refinements, maintenance around the O2 system work (~0930 – 1500)
DIAL prepped for calibration

Wednesday, 6/12, Plans:
06:00 A/C access (O2 work likely to start before 8; estimated 2 hrs; time your arrival accordingly)
13:00 Lab meeting (daily)
17:30 Access ends