[Arcsix] POD August 15, 2024 - Flight Day (SF#9 P-3, SF#10 LearJet, SF#5 G-III)

Phothisane, Stevie (ARC-SGP)[Bay Area Environmental Research Institute (BAER)] s.s.phothisane at nasa.gov
Wed Aug 14 16:48:29 PDT 2024


POD August 15, 2024 - Flight Day (SF#9 P-3, SF#10 LearJet, SF#5 G-III)



All:

0415 - Go No-Go (WhatsApp message, Flight Ops Channel)

1600 - Flight Debrief (Hangar 8 conference room)



P-3 Schedule:

0430 - P-3 Power and Instrument Access (if No-go revert to 0800-1600 access)

0700 - Preflight Briefing (Hangar 8 conference room)

0720 - Doors Close

0800 - Takeoff

~TBD - Landing (approximate time)

1600 - Flight Debrief Brief (Hangar 8 conference room)



G-III Schedule:

0800 - Estimated earliest potential takeoff

~TBD - Landing (approximate time)



Lear Schedule:

0815 - Estimated earliest potential takeoff

~TBD - Landing (approximate time)


General reminders:

  *   For luggage, the staging deadline is noon on tomorrow. If we fly, all flyers must have their luggage ready in the morning before the flight. To make things easier, you can leave your luggage in your building’s common area and ESPO can arrange to pick it up: for 99, in any of the hallways on the first floor; for 331/336, in the living room area. Please have it there no later than 10am if you want ESPO to pick up.
  *   Please bring any fans, tables, or chairs that you are using at 99/331/336 to the common rooms/hallways for ESPO to collect.
  *   Some reminders regarding de-integration at WFF. Note that when we refer to deinstallation or de-integration, both refer to the complete removal of all racks, probes, tubing, and other scientific equipment from the aircraft.
     *   The plan is as follows:
        *   Saturday: Instrument teams can begin removing the racks on the left side of the P-3 to allow the LARGE equipment to be taken out. If time permits, teams can start removing the rest of the racks, but the focus for Saturday will be clearing space for LARGE so they can be ready for PACE-PAX.
        *   Sunday: No work is planned and will be a hard down day for the P-3 crew.
        *   Following Monday-Friday: Teams will continue the deinstallation process, removing the remaining equipment from the aircraft if they didn’t finish on Saturday.
        *   After AMC Shipment Arrival (Expected First/Second Week of September): Teams can depopulate their racks and prepare their equipment for shipment back to their home institutions once all their crates have arrived. Please work with Kelly Griffin regarding any shipments from Wallops back to your home institutions.
  *   Fill out this Google Form<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fforms.gle%2FcjxTpTti6C6qZLFK6&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=t1D7WitpJBHbnXKfrJzIIYQ4JL8vYdGLC%2BfVcskcuU0%3D&reserved=0> so we can track how you plan to depart Pituffik. If it applies, indicate if you plan to disembark in Burlington, VT, or Bangor, ME. At the end, you can also specify any general logistical needs ESPO can help.


=======================

Online connection information:

Join Zoom Meeting

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcuboulder.zoom.us%2Fj%2F96321353157&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=I0oG6Zb1GEPTbYzMXnZj%2Fj4dS2Q3T8ixxLasd5NS8bo%3D&reserved=0<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcuboulder.zoom.us%2Fj%2F96321353157&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=I0oG6Zb1GEPTbYzMXnZj%2Fj4dS2Q3T8ixxLasd5NS8bo%3D&reserved=0>

Meeting ID: 963 2135 3157

Phone: +15642172000,,96321353157# US


WhatsApp groups - https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fchat.whatsapp.com%2FJN6nX8KCyEADl1PLjo38hl&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=NWgtmgtfPa%2FMIDzYk1mlsT5YBmF5kCDWywZZrF0tzgw%3D&reserved=0<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fchat.whatsapp.com%2FJN6nX8KCyEADl1PLjo38hl&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=NWgtmgtfPa%2FMIDzYk1mlsT5YBmF5kCDWywZZrF0tzgw%3D&reserved=0>


ARCSIX Shared Google Photo Album - https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fphotos.app.goo.gl%2FDAeoXEHasbHGtMok9&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=%2B%2Ft%2B4Ty0YPSkb7KujARjnzzJ1TStPzd2C4vb8ftvQzA%3D&reserved=0<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fphotos.app.goo.gl%2FDAeoXEHasbHGtMok9&data=05%7C02%7CArcsix%40espo.nasa.gov%7C8ab40134df1e43d4d8ad08dcbcbba1ae%7C7005d45845be48ae8140d43da96dd17b%7C0%7C0%7C638592761320812905%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=%2B%2Ft%2B4Ty0YPSkb7KujARjnzzJ1TStPzd2C4vb8ftvQzA%3D&reserved=0>


ESPO On Site:

Stevie Phothisane +1 (707) 772-9683

Quincy Allison +1 (650) 455-4964

=======================

Photo of the day…
[cid:image001.jpg at 01DAEE82.DD7B5EA0]
The ARCSIX-2 team getting ready for a photo shoot with all 4 aircraft supporting this mission. Not pictured is the P-3 to the left, and C-130 on the right. Final, edited, and remastered group photo with all 4 aircraft will be sent out soon.
Photo credit – Stevie Phothisane (ESPO)


--
Stevie Phothisane (He/Him)
Deputy Project Manager/Logistics
Earth Science Project Office (ESPO)
NASA Ames Research Center
Bay Area Environmental Research Institute
+1 (707) 772-9683 mobile/WhatsApp
s.s.phothisane at nasa.gov<mailto:s.s.phothisane at nasa.gov> // phothisane at baeri.org<mailto:phothisane at baeri.org>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/arcsix/attachments/20240814/0c80bcef/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 4390400 bytes
Desc: image001.jpg
URL: <http://espo.nasa.gov/pipermail/arcsix/attachments/20240814/0c80bcef/attachment-0001.jpg>


More information about the arcsix mailing list