ARCSIX team-

It came to my attention yesterday that some folks weren't aware that the test flight(s) had been moved up so teams had full access to their equipment in the event that something went wrong, so I wanted to share the remainder of the complete ARCSIX schedule up to deployment.

      29 April- 3 May     MARLi, wing instruments, ADL, GVR tail mods
      6-10 May               Wing instruments, GVR installation
      10 May                  Final Airworthiness Review
      13 May                  Final Configuration Review and Pressure Check
      14 May                  Flight Readiness Review and Weight & Balance
      15 May                  Compatibility Flight Profile flight (engineering check flight- aircrew ONLY)
      16 May                  Operational Readiness Review
      17 May                  Instrument Check Flight (all instruments and operators)
                                        ** DUE DATE FOR "CHECKED" LUGGAGE AT WFF **
      20 May                  C-130 packed for cargo run
      21 May                  C-130 travels to Pituffik to offload ARCSIX cargo
      22 May                  C-130 returns to WFF
      23 May                  Aircraft pack day for P-3 and C-130
      24 May                  Transit day for P-3 and C-130
                   Note: C-130 stops at Burlington International airport to pick up additional QNCs, P-3 travels directly to Pituffik Space Base

If anyone has questions please don't hesitate to contact me!

Have a great day,

Kelly Griffin
P-3 Project & Mission Manager
Wallops Flight Facility Aircraft Office
Yulista Solutions, LLC
757-854-7623 (o)
757-894-4985 (c)





-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/arcsix/attachments/20240425/a4c462ac/attachment.htm>


More information about the arcsix mailing list