Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

HS3 08/12/14 Daily Schedule

Overview:

-          AV-1 passed CST

-          AV-6 replacement nose-gear being replaced

 

Today’s Accomplishments:

-          AV-1 CST completed successfully

-          AV-1 Payload GPS issue repaired

-          AV-6 Low-light Camera issue repaired

-          AV-6 Nose Gear replacement

-          HS3 Dry Run continues

 

Plan for Wednesday – AV-1 Pre-flight

-          0645 – 0900: AV-1 Comm’s Test w/GHOC-E

o   No P.I. involvement

o   Crew, Data-IT: see Chris N’s Schedule

-          0800 PDT (1100 EDT): Dry Run continues

-          0900: AV-1 Inst. Preflight in Hangar

-          1100: Aircraft Preflight continues

 

Plan for Thursday – AV-1 Range Flight (Times shown are local)

-          AFRC (PDT):

o   0500: T-0 Briefing for Range Flight

o   0530: Crew in GHOC

o   0545: Engine Start

o   ~0600: Take off

§  Est. Flight Time: 5-6 hrs

o   0800: Dry Run continues

-          WFF (EDT):

o   0830: AV-1 P.I.’s in GHOC-E

o   ~0900: Takeoff

o   1100: Dry Run continues

 

Outlook:

-          Fri: HS3 MRR (WebEx and Phone)

-          19-20 Aug: AV-1 Transit to WFF (Aft. T.O., overnight flight)

-          21-22 Aug: AV-6 Transit to WFF (Aft. T.O., overnight flight)