The GLOPAC website is undergoing a major upgrade that began Friday, October 11th at 5:00 PM PDT. The new upgraded site will be available no later than Monday, October 21st. Until that time, the current site will be visible but logins are disabled.
Home > ATTREX 02/17/15 Mission Daily Schedule
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
ATTREX 02/17/15 Mission Daily Schedule
Overview:
- MMS and GHOST wiring issues resolved, outdoor Satcom Testing continues tomorrow.
- Expectation of Pre-CST by COB tomorrow.
- P.I.’s - see arrival schedule below to support testing and Pre-CST
Accomplishments:
- NGC reports CAST/ATTREX payload passes shear-bending analysis
- GHOST Cryostat cool-down and re-installation on aircraft
- MMS wiring and GHOST IT issues resolved
- Tech Brief Slide run-through
- Weekly CAST/ATTREX Leads Telecom
Issues/Watch items:
- MMS wiring issue required all day to resolve – no outdoor Satcom Testing accomplished today.
Upcoming Schedule:
Wednesday:
- Crew to stage aircraft at normal Ku-testing location, ready for power at 0730
- MMS, GHOST, AIITS & Hawkeye: please report to GHOC at 0730
- O3, NWV, MTP & GWAS: please report to Payload Cage at 0900 (You’ll be called to GHOC as needed by Caitlin)
- Aircraft outdoor testing all day hopefully concluded with Pre-CST.
Thursday:
- Maint and Avionics aircraft final prep for CST
Friday:
- All personnel participate in CST: Schedule TBA