Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
NASA - NOAA Plan of the Day
Monday, August 14:
0830: ESPO on deck
1030: Forecasting Meeting (Flight Operations Center at Courtyard Marriott and Webex)
NASA DC-8
0900-0930: PALMS & CIT-CIMS servicing
0930-1730: Instrument Access
**The ESPO Science truck is scheduled to depart on Wednesday, 8/16, to arrive back in Palmdale by Saturday, 8/19, in preparation for flights starting Monday, 8/21. Instrument teams should plan to have as much cargo packed in its cases and ready to ship by 1200 on Tuesday. Let ESPO know if you have any questions or concerns.
NASA LaRC G-III
0900 Instrument access begins
NASA JSC G-V
GV access will be coordinated as needed.