ATom
Thursday, 3/15 Accomplishments
AMP, ATHOS, QCLS, MMS, TOGA, CAFS, DLH, PALMS, Picarro, SAGA and SP2 completed installations
NOyO3 installed, working pump issue
SOAP installed, conducted power checks then removed for shipping to DEN tonight
S02 installed, conducted power checks, a couple issues remain to be resolved
CAPS installation ongoing
Egress training
Wednesday, 3/14 Accomplishments
ATHOS, AMP, CAFS, DLH, MMS, NOyO3, PALMS, Picarro, QCLS, SAGA and TOGA installed
Power checks ongoing (QCLS, Picarro and DLH complete)
CAPS team arrived
Thursday, 3/15 Plan
Continue installations and power checks
All ATom-4 Deployment Guides now available on website:
https://espo.nasa.gov/atom/deployment_guides
Tuesday, 3/13 Accomplishments
NOyO3, QCLS, DLH, Picarro, TOGA, MMS, ATHOS, SAGA and CAFS mechanically installed
Wednesday, 3/14 Plan
NO on the plane in the forward pit
Check with crew prior to first boarding A/C
06:00-17:00 A/C access
Install PALMS, AMP and PANTHER/UCATS rack
Power checks
The Atom-4 deployment is underway!
Tuesday, 3/13 Plan
06:00-18:00 A/C access
- Window plates installed, ready for probes
- See Terrance for all your cabling needs
- Check with Richard Wong for pressure system requirements
- Check with Marion or Chris Jennison for laser system requirements
Weekend A/C access TBD