Thursday, March 29 Accomplishments
- GT-CIMS, NOAA CIMS, and CIT-CIMS installed and power checked
- PANTHER/UCATS running instruments in lab
Friday, March 30 Plan
- WAS to continue integration
- 06:00 - 09:00: A/C outside for testing.
Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow
Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF
Tuesday, 3/20 Accomplishments
AO2/Medusa finished installed plumbing and powered up
CAPS cross computer calibrations and systems checks
GT-CIMS staged shipping material and began to unpack
HR-AMS installed and conducted power checks and alignment
ISAF completed mechanical installation and began cabling
Shipment preparations
Monday, 3/19 Accomplishments
AO2/Medusa, ISAF and HR-AMS arrived
AO2/Medusa installed and powered on
ISAF installed
HR-AMS calibrating in lab
Tuesday, 3/20 Plans
06:00-17:30 A/C access
HR-AMS planning to install
Monday, 3/19 Plan
07:00 Badge office opens (for those with expired badges)
06:00-18:00 A/C access
CAPS installation continues
AO2/Medusa, HR-AMS, ISAF teams begin installations
Friday, 3/16 Accomplishments
All first round instruments installed
No NOyO3 issues
CAPS installation complete
Monday, 19 Plan
ISAF, AO2/Medusa & HR-AMS begin installations