2016-10-31

Note:  Chairs and Tables with "KS" on them can be put in the Science Trailer.  Chair and Tables with blue painters tape are United and can be folded up in place.

Monday, Oct 31st – WB-57 Transit
0730 Mission Brief
0900 Estimated Take-off 
1420 Estimated Landing at Kwajalein (in Guam time)
1530 Deadline to put items in Hangar Staging area for Quickship
1615 Quickship Pickup

Tuesday, Nov 1st
1200 ISUs Pack Up complete
Composite Room Clean Up
1200 2nd floor office Pack Up complete (Frig, Microwave, Printer, etc leaving)
Suit trailer & Science trailer pickup

Wednesday, Nov 2nd
0730 ISUs Picked Up

2016-10-30

Accomplishments
9 spectacular science flights!
WB-57 Landed in Kwajalein
Quickship Picked Up
Composite Rooms and Trailers empty
ISUs Packed Up

Tuesday, Nov 1st
1200 2nd floor office Pack Up complete (Frig, Microwave, Printer, etc leaving)
Suit trailer & Science trailer pickup

Wednesday, Nov 2nd
0730 ISUs Picked Up

Thank you everyone for a great mission!
Final POD!

2016-10-30

NOTE:  Additional info on road closures tomorrow has created more concern about getting into the hangar in the morning so access times 
will be later so teams can avoid the potential traffic problems.

NOTE:  The Sunday science meeting has been canceled.

NOTE:  The is a Rave tonight at the Sheraton so be prepared for difficulties parking.

Sunday, October 30th – No Fly / Pack
1100-1500 Aircraft Access with power

Monday, October 31st – WB-57 Transit
0700-0800 Instrument Upload
0800 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1000 Estimated Take-off
1500 Estimated Landing at Kwajalein
1530 Deadline to put items in Hangar Staging area for Quickship
1600 Quickship Pickup

Tuesday, November 1st - ISU Pack
Composite Room clean up
2nd floor office packup (Frig, Microwave, Printer, etc leaving)
Suit trailer & Science trailer pickup

Packing Note:  Items returning in ISUs can be placed in ISUs when ready.  Items for the Quick Ship should be placed in the staging area in the hangar ASAP.  See Ron for details.

2016-10-29

Saturday, October 29th - Down Day  

Sunday, October 30th – No Fly / Pack
0730-1000 Aircraft Access with power
0900 - Marilyn will poll teams to determine afternoon access requirements.
1000 Science Meeting  (Tell Ru-Shan/Eric if you have a science presentation)
1100-1400 Aircraft Access window as needed.

Monday, October 31st – WB-57 Transit
0700-0800 Instrument Upload
0800 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1000 Estimated Take-off
1500 Estimated Landing at Kwajalein
1530 Deadline to put items in Hangar Staging area for Quickship
1600 Quickship Pickup

Tuesday, November 1st - ISU Pack
Composite Room clean up
2nd floor office packup (Frig, Microwave, Printer, etc leaving)
Suit trailer & Science trailer pickup

Packing Note:  Items returning in ISUs can be placed in ISUs when ready.  Items for the Quick Ship should be placed in the staging area in the hangar ASAP.  See Ron for details.

2016-10-28

Friday, October 28th - Planned Fly Day #9
0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download

Saturday, October 29th - Down Day / Pack 

Sunday, October 30th – No Fly / Pack

Monday, October 31st – WB-57 Transit

Packing Note:  Items returning in ISUs can be placed in ISUs when ready.  Items for the Quick Ship can be placed in the staging area in the hangar.  See Ron or WhatsApp for details.

2016-10-27

Accomplishments:
Science Flight #8 
See attached pictures of Dom's "Office" and a picture Mark took of the contrails as the plane circiling on descent.

Thursday, October 27th - No Fly Day

0900-1000 Science/Weather Brief - Tell Ru-Shan/Eric if you have a science presentation
1000-1400 Aircraft Access with power

Friday, October 28th - Possible Fly Day #9
0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download

Saturday, October 29th - Down Day / Pack

Sunday, October 30th – No Fly / Pack

Monday, October 31st – WB-57 Transit

2016-10-26

Accomplishments:
Science Flight #7
Balloon Launch #4

Wednesday, October 26th - Flight Day #8
0800-0900 Instrument Upload
0930 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1130 Estimated Take-off
1700 Estimated Landing
1730 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1730-1900 Instrument Download

Thursday, October 27th - No Fly Day

0900-1000 Science/Weather Brief - Tell Ru-Shan/Eric if you have a science presentation
1000-1400 Aircraft Access with power

Friday, October 28th - Possible Fly Day #9
0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download

Saturday, October 29th - Down Day / Pack

Sunday, October 30th – No Fly / Pack

Monday, October 31st – WB-57 Transit

2016-10-25

Accomplishments:
Functional Check Flight successfully completed

Tuesday, October 25th - Fly Day #7

0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
~1200  Hosted Lunch with United Maintenance
1400 Possible Balloon launch
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download

Wednesday, October 26th - Possible Fly Day #8

0700-0800 Instrument Upload
0830 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1030 Estimated Take-off
1600 Estimated Landing
1630 Post Flight Brief (Send rep or inform Ru-Shan instrument update so download is not delayed)
1630-1800 Instrument Download

Thursday, October 27th - No Fly Day
Friday, October 28th - Possible Fly Day #9

2016-10-24

Accomplishments:
Low and High power engine runs were completed on Saturday and aircraft ready for FCF on Monday.
Monday, October 24th – Functional Check Flight
0730-0900 Instrument Upload
0900 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1000 Estimated Take-off
1130 Estimated Landing
1200-1400 Instrument Download
1400 Group Photo
1430 Science Meeting (If you have data you would like to present, contact Ru-Shan.)

Tuesday, October 25th - Possible Fly Day #7
Hosted Lunch with United Maintenance

Wednesday, October 26th - Possible Fly Day #8

2016-10-23

FYI:  Media Day is TBD
Sunday, October 23rd – Down Day

Monday, October 24th – Functional Check Flight
0730-0900 Instrument Upload
0900 Mission Brief (Ru-Shan will represent Science.  Each instrument team can let Ru-Shan know their instrument fly status.)
1000 Estimated Take-off
1130 Estimated Landing
1200-1400 Instrument Download
1400 Group Photo
1430 Science Meeting (If you have data you would like to present, contact Ru-Shan.)

Tuesday, October 25th - Possible Fly Day #7

Pages

Subscribe to Daily Schedule