[Wvb] ER-2 809 Status for Sunday, 18-September

Norlin, Ken A. (AFRC-PS) ken.a.norlin at nasa.gov
Sun Sep 18 01:00:23 PDT 2016


ER-2 is airborne at 0959

-----
Ken Norlin
ER-2 Mission Manager
NASA Armstrong Flight Research Center
(661) 276-2046  (661) 816-6458 (cell)
ken.norlin at nasa.gov

> On Sep 17, 2016, at 12:39 PM, Norlin, Ken A. (AFRC-PS) <ken.a.norlin at nasa.gov> wrote:
> 
> All,
> 
> The ER-2 plan for Sunday is to fly ORACLES Science Flight #5 at Walvis Bay, Namibia.
> 
> The current checklist (v5.3) is attached.
> 
> Timeline:
> 
> 0630 WAST (0430Z):   Crew Show/Hands-On
> 0700 WAST (0500Z):   Mission / Weather Brief - Telecom number: 720-259-6462 code: 130634#  (+1 (720) 259-6462,,,,130634#)
> 
> 0730 WAST (0530Z):   Hands-Off
> 0930 WAST (0730Z):   Engine Start
> 1000 WAST (0800Z):   Takeoff
> 
> 1830 WAST (1630Z):   Landing (~8.5-hour duration)
> 1900 WAST (1700Z):   Hands-On
> 2000 WAST (1800Z):   Hands-Off
> 
> 
> Pilot:      Stu Broce 661-816-4053 
> Mobile:  Greg Nelson 661-483-4358 / Jan Nystrom 661-271-7537
> 
> INMARSAT/NASDAT: Carl Sorenson 408-239-3785
> 
> AirMSPI:  Brian Rheingans 909-263-6843
>                 Gerard Van Harten +264 818 573 722
> 
> SSFR:  Warren Gore 650-995-3933
> 
> HSRL-2: Tony Cook 757-367-9144
>               Dave Harper 757-349-3679
> 
> eMAS:  Rose Dominguez: 650-316-0383
>              Pat Grant: 650-224-9187
> 
> RSP:  Brian Cairns +264 818 573 734
>          Kirk Knobelspiesse 917-355-4546 
>          Jackek Chowdhary    +1 646 382 4864
> 
> Crew Chief:             Pat Lloyd 661-810-8969
> Quality Inspector:  Clark Johnson 661-599-6836
> 
> Mission Manager: Ken Norlin 661-816-6458
> Project Manager:  Brian Hobbs 661-221-8235
> 
> 
> -----
> Ken Norlin
> ER-2 Mission Manager
> NASA Armstrong Flight Research Center
> (661) 276-2046   (661) 816-6458 (cell)
> ken.norlin at nasa.gov
> 
> <Checklist_ORACLES_v5.3.docx>



More information about the wvb mailing list