As we discussed on the telecon today, here's the current schedule for the ER-2 upload:

7/22 (Fri)              - Complete RSP upload
7/25 (Mon)          - Complete HSRL-2 upload
7/26 (Tue)           - Conduct CST (engine run on ramp) - around 9AM
7/27 (Wed)          - Conduct check flight (~3 hours), 9AM takeoff
7/28 (Thu)           - Instrument checks as needed
7/29 (Fri)              - AFRC RDO (day off)
8/1 (Mon)            - Instrument checks as needed
8/2 (Tue)              - Conduct final check flight (~3 hours), 9AM takeoff
8/3 (Wed)            - Prepare air shipment for Namibia

Please have notional flight plans to Tim as soon as you can.  He'll need the plans for Wednesday's check flight by 2PM on Monday.

I've attached the draft checklist for the check flight - please let me know if I missed anything.

Thanks,
Ken

-----
Ken Norlin
ER-2 Mission Manager
NASA Armstrong Flight Research Center
(661) 276-2046   (661) 816-6458 (cell)
ken.norlin at nasa.gov<mailto:ken.norlin at nasa.gov>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/oracles-er2-investigators/attachments/20160721/7a6fd61e/attachment-0002.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Checklist_ORACLES_16.07.27_draft.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 33774 bytes
Desc: Checklist_ORACLES_16.07.27_draft.docx
URL: <http://espo.nasa.gov/pipermail/oracles-er2-investigators/attachments/20160721/7a6fd61e/attachment-0002.docx>


More information about the oracles-er2-investigators mailing list