END OF DAY REPORT 4/24: Sunday
Progress AFRC DC-8
ESPO packed the remaining instrument equipment and baggage to be picked up and shipped to Osan AB tomorrow morning at 0900.
------------------------ Schedule:
4/25: Monday
0700 –1400 Aircraft access – Instruments must be installed buttoned up and ready to fly!!
4/26: Tuesday - Transit to Osan DC-8
0200 Aircraft access
0330 Preflight aircraft and instruments
0400 Pre-flight brief
0530 Takeoff— ETA 1330 Osan AB
READ THIS- If you need a ride from your hotel, Tuesday morning, but have not yet signed the ride sheet do so ASAP. Mark if you need an early or late pick up. (Early=0200, Late=0300) Drop off your rental cars on the 25th and we coordinate shuttles to the hangar on the early morning of the 26th. We have the Big Blue Van for those who need a ride. Tim Moes or Kent or any civil servant can drive the van. There are also carpool opportunities to the hangar with folks who are not departing with the airplane. Please use the sign up sheet in the lab for carpool or van.
NOTES: TOOL CONTROL = All Tools must be returned and signed off before each flight INSPECTION = All Instruments must be secured and inspected before the flight. Weight/Balance = Anytime equipment is removed or installed on the aircraft it must be documented for weight and balance on the log sheet posted in the aircraft. EGRESS Training = Contact Matt Berry if you have not had training and plan on flying on the DC-8 for the test or transit flight. • Lab meeting 1300 every day except Saturday and Sunday.
Follow KORUS-AQ on TWITTER = https://twitter.com/KORUS_AQ/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/korus-aq-updates/attachments/20160425/49b474a0/attachment-0002.html>
More information about the korus-aq-updates
mailing list