[Korus-aq-updates] KORUS Plan for April 12
Vasques, Marilyn F. (ARC-SGG)
marilyn.vasques at nasa.gov
Mon Apr 11 15:05:18 PDT 2016
PLAN FOR 4/12:
0600 - 1700: Instrument Integration CIT-CIMS, GT-CIMS, K-ACES, K-CIMS, and K-PTR-MS.
END OF THE DAY REPORT:
DC-8:
CIT-CIMS: Installed.
GT-CIMS: Ready for power check.
K-ACES: Installed.
K-CIMS: Ready for power check.
K-PTRMS: Installed.
Several instruments have open issues and documentation to complete prior to Friday shake down flight.
NOTES:
• Lab meeting 1300 every day except Saturday and Sunday.
LaRC B200: (by Lucille Crittenden)
• The science instruments were installed on the aircraft, finishing up just after noon today.
• Due to inspections still to complete and a lot of paperwork still to close out , an ICF today was not possible. Scientists were posed to do more ground checks to verify their systems this afternoon.
• An ICF will be conducted once the aircraft reaches Korea.
• Current plan is to remove the science instruments and begin their pack up tomorrow afternoon.
• AirMods will arrive mid-morning on Wednesday to start the fuel tank installation which will take approximately 2 days. Hope to be able to get a check flight with the external tanks on Friday.
• At this time, it still looks like a transit date of 18April.
-- Marilyn Vasques
ESPO Director
NASA Ames Research Center
MOBILE: 650-417-8796
OFFICE: 650-604-6120
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/korus-aq-updates/attachments/20160411/fb661a1d/attachment-0002.html>
More information about the korus-aq-updates
mailing list