[Korus-aq-updates] KORUS Plan for April 12

Vasques, Marilyn F. (ARC-SGG) marilyn.vasques at nasa.gov
Mon Apr 11 15:05:18 PDT 2016


PLAN FOR 4/12:
0600 - 1700: Instrument Integration CIT-CIMS, GT-CIMS, K-ACES, K-CIMS, and K-PTR-MS.

END OF THE DAY REPORT:
DC-8:
CIT-CIMS: Installed.
GT-CIMS:  Ready for power check.
K-ACES:  Installed.
K-CIMS:  Ready for power check.
K-PTRMS:  Installed.
Several instruments have open issues and documentation to complete prior to Friday shake down flight.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.

LaRC B200: (by Lucille Crittenden)
•  The science instruments were installed on the aircraft, finishing up just after noon today.
•  Due to inspections still to complete and a lot of paperwork still to close out , an ICF today was not possible. Scientists were posed to do more ground checks to verify their systems this afternoon.
•  An ICF will be conducted once the aircraft reaches Korea.
•  Current plan is to remove the science instruments and begin their pack up tomorrow afternoon.
•  AirMods will arrive mid-morning on Wednesday to start the fuel tank installation which will take approximately 2 days. Hope to be able to get a check flight with the external tanks on Friday.
•  At this time, it still looks like a transit date of 18April.




-- Marilyn Vasques
ESPO Director
NASA Ames Research Center
MOBILE:  650-417-8796
OFFICE:  650-604-6120

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/korus-aq-updates/attachments/20160411/fb661a1d/attachment-0002.html>


More information about the korus-aq-updates mailing list