[Korus-aq-updates] KORUS Plan for April 9

Vasques, Marilyn F. (ARC-SGG) marilyn.vasques at nasa.gov
Fri Apr 8 15:28:55 PDT 2016


PLAN FOR 4/9:
0700 - 1700: Instrument Integration CAFS, CIT-CIMS, DIAL, GT-CIMS, HR-AMS, K-ACES, K-AMS, K-CIMS, K-PTR-MS, and PTR-MS.

END OF THE DAY REPORT:
DC-8:
CAFS: Rack shared with K-ACES will be ready Monday.
CIT-CIMS: Installed.
DIAL: Ready for laser calibration 4/13.
GT-CIMS:  Ready for power check 4/9.
HR-AMS:  Ready for power check 4/9.
K-ACES:  Lab work this weekend.  Plan to install Monday.
K-AMS: Installed. Ready for calibration.
K-CIMS:  Ready for power 4/9.
K-PTRMS:  Plan to install Monday.
PTR-MS:  Power check complete.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.
•  If you are working on the plane near HR-AMS, please turn off your cell phone, the signal causes interference.

LaRC B200: (by Lucille Crittenden)
Great news from the UC-12 team today!!
•We just finished the Flight Readiness Review minutes ago.  The pilots are preparing to fly the Functional Check flight within the hour!
•Once I receive word from the pilots after the completion of the FCF (anticipate a 2 hour flight), I will send out another email later this evening giving the Go/No-Go decision on starting instrument installation in the morning.  Kudos to everyone on a fantastic job reaching this milestone!
-- Marilyn Vasques
ESPO Director
NASA Ames Research Center
MOBILE:  650-417-8796
OFFICE:  650-604-6120

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/korus-aq-updates/attachments/20160408/b2037030/attachment-0002.html>


More information about the korus-aq-updates mailing list