[Firex-aq] FIREX-AQ DC-8 Plan of the Day
Jordan, Dave E. (ARC-SGG)
dave.e.jordan at nasa.gov
Fri May 31 17:32:07 PDT 2019
Friday, 5/31 Accomplishments:
SP2 completed integration
CAMS, DLH/DACOM, HR-AMS2, GT-CIMS and PTR-MS continued A/C integration
Saturday, 6/1 Plans:
07:00 A/C access
CARE to receive new circuit board and begin replacement/checkout
15:00 A/C access ends
Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez
[cid:491BFD48-8632-4094-94C8-613BA998D551 at nasa.gov]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190601/acbc63c7/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Screen Shot 2019-05-31 at 2.32.06 PM.png
Type: image/png
Size: 2015764 bytes
Desc: Screen Shot 2019-05-31 at 2.32.06 PM.png
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190601/acbc63c7/attachment-0001.png>
More information about the Firex-aq
mailing list