Friday, 5/24 Accomplishments:
PTR-MS and CARE, CAFS, LARGE and mini-DOAS shared rack installed on A/C
mini-DOAS instrument removed from rack for lab work
LINEPH on A/C; awaits mounting plate (~6/9)

At the end of the week we’ve got:  NOyO3, CAFS, DLH/DACOM, AOP, SAGA,
the LARGE, CAFS, CARE, mini-DOAS and AS-TEM shared rack and PTR-MS installed.

Saturday, 5/25 Plan:
07:00 A/C access
General instrument integration work continues
15:00 A/C access ends

Sunday & Monday (5/26 & 5/27):
Lab access, no A/C access

[cid:E1D3EA80-FF1E-49D8-A724-6FF138AFF0FC at ndc.nasa.gov]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190524/97a9bf5b/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Screen Shot 2019-05-24 at 2.41.33 PM.png
Type: image/png
Size: 1361642 bytes
Desc: Screen Shot 2019-05-24 at 2.41.33 PM.png
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190524/97a9bf5b/attachment-0001.png>


More information about the Firex-aq mailing list