[Firex-aq] FIREX-AQ DC-8 Plan of the Day

Jordan, Dave E. (ARC-SGG) dave.e.jordan at nasa.gov
Wed May 22 18:03:47 PDT 2019


Wednesday, 6/22 Accomplishments
AOP physically installed
Instrument installation work continued
Working on getting power to racks
LARGE instrument reconfiguring rack to satisfy overturning moment

Thursday, 6/23 Plan
06:00 A/C access
Instrument installation work continues
Mini-DOAS team arrives
17:30 A/C access ends

Send heater schematics to Brennan Wehr and Paul Martinez
Send pressure system schematics to Richard Wong
Put copies of approved drawings on rack clipboard
[cid:DC428D9E-122C-47F8-8E21-AF40742F2856 at nasa.gov][cid:EADFEA7C-6F21-4C93-B3B1-21FDD6E56319 at nasa.gov]


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190523/0907bdab/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IMG_0896.jpeg
Type: image/jpeg
Size: 55171 bytes
Desc: IMG_0896.jpeg
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190523/0907bdab/attachment-0002.jpeg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IMG_2390.jpeg
Type: image/jpeg
Size: 52264 bytes
Desc: IMG_2390.jpeg
URL: <http://espo.nasa.gov/pipermail/firex-aq/attachments/20190523/0907bdab/attachment-0003.jpeg>


More information about the Firex-aq mailing list