From: "Scofield, Chris (ARC-SG)" <chris.scofield at nasa.gov>
Date: Tuesday, June 21, 2022 at 10:09 AM
To: Marilyn Vasques <marilyn.vasques at nasa.gov>, "Fladeland, Matthew M. (ARC-SG)" <matthew.fladeland at nasa.gov>, Evelyn Perez <evelyn.t.perez at nasa.gov>, "Nguyen, Nga H. (ARC-CPM)[Logical-R Joint Venture, LLC]" <nga.nguyen at nasa.gov>, "Spackman, Ryan (ARC-S)" <ryan.spackman at nasa.gov>
Cc: "Schwandner, Florian M. (ARC-SG)" <florian.m.schwandner at nasa.gov>, "Ly, Diana C. (ARC-SG)" <diana.c.ly at nasa.gov>
Subject: FW: 6-3-22 N232 Project Updates
FYI.
Marilyn-
Please share as you determine appropriate, with any ESPO folks effected.
Chris
From: "Martin, Rodney A. (ARC-TI)" <rodney.martin at nasa.gov>
Date: Friday, June 17, 2022 at 4:24 PM
To: "Hogan, Roxana L. (ARC-JCM)" <roxana.hogan at nasa.gov>, "Scofield, Chris (ARC-SG)" <chris.scofield at nasa.gov>, "Hunter, Tracy G. (ARC-CF)" <tracy.g.hunter at nasa.gov>, "Crisolo, Jonathan S. (ARC-CFR)" <jonathan.s.crisolo at nasa.gov>, "Atkins, Nancy (ARC-PX)[WYLE LABS]" <nancy.atkins at nasa.gov>, "Rudisel, Carolina. (ARC-D)" <carolina.rudisel at nasa.gov>
Cc: "Belanger, Lorin D. (ARC-JCM)" <lorin.d.belanger at nasa.gov>, "Pham, Khoi M. (ARC-JCM)" <khoi.m.pham at nasa.gov>, "Jacquemet, Patrick D. (ARC-JCM)" <patrick.d.jacquemet at nasa.gov>, "Navarro, Dagoberto S. (ARC-JCM)" <dagoberto.s.navarro at nasa.gov>, "Chahal, Waheguru S. (ARC-JCM)" <waheguru.s.chahal at nasa.gov>, "Miller, Roger A. (ARC-JCM)" <roger.a.miller at nasa.gov>, "Fearon, Stewart (ARC-JC)" <stewart.r.fearon at nasa.gov>, "Preston, William T. (ARC-JCM)[JACOBS]" <william.t.preston at nasa.gov>, "Farhat, Mark (ARC-JCM)[JACOBS]" <mark.farhat at nasa.gov>, "Stednitz, Kent A. (ARC-JCM)" <kent.a.stednitz at nasa.gov>, "Astorga, Emigdio G. (ARC-JCM)" <emigdio.g.astorga at nasa.gov>, "Berber, Daniel L. (ARC-JCM)[JACOBS]" <daniel.l.berber at nasa.gov>, "Sethna, Shaina V. (ARC-JCM)" <shaina.v.sethna at nasa.gov>, "Wohler, Bill (ARC-PX)[SETI INSTITUTE]" <bill.wohler at nasa.gov>
Subject: RE: 6-3-22 N232 Project Updates
Hi Roxana,
Thanks for helping to get this looked after so promptly. Have a great weekend !
Best,
Rodney
-------- Original Message --------
From: "Hogan, Roxana L. (ARC-JCM)" <roxana.hogan at nasa.gov>
Date: Fri, June 17, 2022 4:20 PM -0700
To: "Martin, Rodney A. (ARC-TI)" <rodney.martin at nasa.gov>, "Scofield, Chris (ARC-SG)" <chris.scofield at nasa.gov>, "Hunter, Tracy G. (ARC-CF)" <tracy.g.hunter at nasa.gov>, "Crisolo, Jonathan S. (ARC-CFR)" <jonathan.s.crisolo at nasa.gov>, "Atkins, Nancy (ARC-PX)[WYLE LABS]" <nancy.atkins at nasa.gov>, "Rudisel, Carolina. (ARC-D)" <carolina.rudisel at nasa.gov>
CC: "Belanger, Lorin D. (ARC-JCM)" <lorin.d.belanger at nasa.gov>, "Pham, Khoi M. (ARC-JCM)" <khoi.m.pham at nasa.gov>, "Jacquemet, Patrick D. (ARC-JCM)" <patrick.d.jacquemet at nasa.gov>, "Navarro, Dagoberto S. (ARC-JCM)" <dagoberto.s.navarro at nasa.gov>, "Chahal, Waheguru S. (ARC-JCM)" <waheguru.s.chahal at nasa.gov>, "Miller, Roger A. (ARC-JCM)" <roger.a.miller at nasa.gov>, "Fearon, Stewart (ARC-JC)" <stewart.r.fearon at nasa.gov>, "Preston, William T. (ARC-JCM)[JACOBS]" <william.t.preston at nasa.gov>, "Farhat, Mark (ARC-JCM)[JACOBS]" <mark.farhat at nasa.gov>, "Stednitz, Kent A. (ARC-JCM)" <kent.a.stednitz at nasa.gov>, "Astorga, Emigdio G. (ARC-JCM)" <emigdio.g.astorga at nasa.gov>, "Berber, Daniel L. (ARC-JCM)[JACOBS]" <daniel.l.berber at nasa.gov>, "Sethna, Shaina V. (ARC-JCM)" <shaina.v.sethna at nasa.gov>
Subject: RE: 6-3-22 N232 Project Updates
Hi Rodney,
Jacobs sent a technician to N232 to investigate the loud motor sound and there appears to be an issue with an exhaust fan. The technician is continuing to troubleshoot at this time.
I will update you as more information is provided.
Thank you,
Roxana
From: Hogan, Roxana L. (ARC-JCM)
Sent: Friday, June 17, 2022 6:24 AM
To: Martin, Rodney A. (ARC-TI) <rodney.martin at nasa.gov>; Scofield, Chris (ARC-SG) <chris.scofield at nasa.gov>; Hunter, Tracy G. (ARC-CF) <tracy.g.hunter at nasa.gov>; Crisolo, Jonathan S. (ARC-CFR) <jonathan.s.crisolo at nasa.gov>; Atkins, Nancy (ARC-PX)[WYLE LABS] <nancy.atkins at nasa.gov>; Rudisel, Carolina. (ARC-D) <carolina.rudisel at nasa.gov>
Cc: Belanger, Lorin D. (ARC-JCM) <lorin.d.belanger at nasa.gov>; Pham, Khoi M. (ARC-JCM) <khoi.m.pham at nasa.gov>; Jacquemet, Patrick D. (ARC-JCM) <patrick.d.jacquemet at nasa.gov>; Navarro, Dagoberto S. (ARC-JCM) <dagoberto.s.navarro at nasa.gov>; Chahal, Waheguru S. (ARC-JCM) <waheguru.s.chahal at nasa.gov>; Miller, Roger A. (ARC-JCM) <roger.a.miller at nasa.gov>; Fearon, Stewart (ARC-JC) <stewart.r.fearon at nasa.gov>; Preston, William T. (ARC-JCM)[JACOBS] <william.t.preston at nasa.gov>; Farhat, Mark (ARC-JCM)[JACOBS] <mark.farhat at nasa.gov>; Stednitz, Kent A. (ARC-JCM) <kent.a.stednitz at nasa.gov>; Astorga, Emigdio G. (ARC-JCM) <emigdio.g.astorga at nasa.gov>; Berber, Daniel L. (ARC-JCM)[JACOBS] <daniel.l.berber at nasa.gov>; Sethna, Shaina V. (ARC-JCM) <shaina.v.sethna at nasa.gov>
Subject: RE: 6-3-22 N232 Project Updates
Hi Rodney,
Thank you for the information. I checked all the N232 trouble calls placed since January and could not find one for Rm 114 or for a loud motor/sound. I went ahead and placed a trouble call this morning for the issue and will track the resolution.
If you have any of the trouble call ticket numbers, or the dates they were placed, or the name (s) of the person who placed them, I can research further.
Will keep you updated.
Thank you,
Roxana
From: Martin, Rodney A. (ARC-TI) <rodney.martin at nasa.gov<mailto:rodney.martin at nasa.gov>>
Sent: Thursday, June 16, 2022 7:40 PM
To: Hogan, Roxana L. (ARC-JCM) <roxana.hogan at nasa.gov<mailto:roxana.hogan at nasa.gov>>; Scofield, Chris (ARC-SG) <chris.scofield at nasa.gov<mailto:chris.scofield at nasa.gov>>; Hunter, Tracy G. (ARC-CF) <tracy.g.hunter at nasa.gov<mailto:tracy.g.hunter at nasa.gov>>; Crisolo, Jonathan S. (ARC-CFR) <jonathan.s.crisolo at nasa.gov<mailto:jonathan.s.crisolo at nasa.gov>>; Atkins, Nancy (ARC-PX)[WYLE LABS] <nancy.atkins at nasa.gov<mailto:nancy.atkins at nasa.gov>>; Rudisel, Carolina. (ARC-D) <carolina.rudisel at nasa.gov<mailto:carolina.rudisel at nasa.gov>>
Cc: Belanger, Lorin D. (ARC-JCM) <lorin.d.belanger at nasa.gov<mailto:lorin.d.belanger at nasa.gov>>; Pham, Khoi M. (ARC-JCM) <khoi.m.pham at nasa.gov<mailto:khoi.m.pham at nasa.gov>>; Jacquemet, Patrick D. (ARC-JCM) <patrick.d.jacquemet at nasa.gov<mailto:patrick.d.jacquemet at nasa.gov>>; Navarro, Dagoberto S. (ARC-JCM) <dagoberto.s.navarro at nasa.gov<mailto:dagoberto.s.navarro at nasa.gov>>; Chahal, Waheguru S. (ARC-JCM) <waheguru.s.chahal at nasa.gov<mailto:waheguru.s.chahal at nasa.gov>>; Miller, Roger A. (ARC-JCM) <roger.a.miller at nasa.gov<mailto:roger.a.miller at nasa.gov>>; Fearon, Stewart (ARC-JC) <stewart.r.fearon at nasa.gov<mailto:stewart.r.fearon at nasa.gov>>; Preston, William T. (ARC-JCM)[JACOBS] <william.t.preston at nasa.gov<mailto:william.t.preston at nasa.gov>>; Farhat, Mark (ARC-JCM)[JACOBS] <mark.farhat at nasa.gov<mailto:mark.farhat at nasa.gov>>; Stednitz, Kent A. (ARC-JCM) <kent.a.stednitz at nasa.gov<mailto:kent.a.stednitz at nasa.gov>>; Astorga, Emigdio G. (ARC-JCM) <emigdio.g.astorga at nasa.gov<mailto:emigdio.g.astorga at nasa.gov>>; Berber, Daniel L. (ARC-JCM)[JACOBS] <daniel.l.berber at nasa.gov<mailto:daniel.l.berber at nasa.gov>>; Sethna, Shaina V. (ARC-JCM) <shaina.v.sethna at nasa.gov<mailto:shaina.v.sethna at nasa.gov>>
Subject: RE: 6-3-22 N232 Project Updates
Hi Roxana,
It has been reported that there's an electrical motor in Rm. 114 (the main electrical switch room) in Bldg. N232 that is very loud and has a high, annoying, pitch when it cycles on, which is most of the time. It's much more noticeable than occupants remember from before the pandemic, who now have to wear headphones and listen to music to keep it from distracting them.
Is it possible that any of the project work that you’ve been diligently providing updates for that are either pending or have been completed may have caused this situation, or that slated to be corrected ? In any case, I wanted to be sure to bring this to your attention, as repeated calls to the service desk have failed to direct attention to the situation.
Best,
Rodney
From: Hogan, Roxana L. (ARC-JCM) <roxana.hogan at nasa.gov<mailto:roxana.hogan at nasa.gov>>
Sent: Friday, June 3, 2022 10:22 AM
To: Martin, Rodney A. (ARC-TI) <rodney.martin at nasa.gov<mailto:rodney.martin at nasa.gov>>; Scofield, Chris (ARC-SG) <chris.scofield at nasa.gov<mailto:chris.scofield at nasa.gov>>; Hunter, Tracy G. (ARC-CF) <tracy.g.hunter at nasa.gov<mailto:tracy.g.hunter at nasa.gov>>; Stanton, Edward L. (ARC-PX) <edward.l.stanton at nasa.gov<mailto:edward.l.stanton at nasa.gov>>; Crisolo, Jonathan S. (ARC-CFR) <jonathan.s.crisolo at nasa.gov<mailto:jonathan.s.crisolo at nasa.gov>>; Atkins, Nancy (ARC-PX)[WYLE LABS] <nancy.atkins at nasa.gov<mailto:nancy.atkins at nasa.gov>>; Laird, Veronica (ARC-D) <veronica.l.laird at nasa.gov<mailto:veronica.l.laird at nasa.gov>>; Rudisel, Carolina. (ARC-D) <carolina.rudisel at nasa.gov<mailto:carolina.rudisel at nasa.gov>>
Cc: Belanger, Lorin D. (ARC-JCM) <lorin.d.belanger at nasa.gov<mailto:lorin.d.belanger at nasa.gov>>; Pham, Khoi M. (ARC-JCM) <khoi.m.pham at nasa.gov<mailto:khoi.m.pham at nasa.gov>>; Jacquemet, Patrick D. (ARC-JCM) <patrick.d.jacquemet at nasa.gov<mailto:patrick.d.jacquemet at nasa.gov>>; Navarro, Dagoberto S. (ARC-JCM) <dagoberto.s.navarro at nasa.gov<mailto:dagoberto.s.navarro at nasa.gov>>; Chahal, Waheguru S. (ARC-JCM) <waheguru.s.chahal at nasa.gov<mailto:waheguru.s.chahal at nasa.gov>>; Miller, Roger A. (ARC-JCM) <roger.a.miller at nasa.gov<mailto:roger.a.miller at nasa.gov>>; Fearon, Stewart (ARC-JC) <stewart.r.fearon at nasa.gov<mailto:stewart.r.fearon at nasa.gov>>; Preston, William T. (ARC-JCM)[JACOBS] <william.t.preston at nasa.gov<mailto:william.t.preston at nasa.gov>>; Farhat, Mark (ARC-JCM)[JACOBS] <mark.farhat at nasa.gov<mailto:mark.farhat at nasa.gov>>; Stednitz, Kent A. (ARC-JCM) <kent.a.stednitz at nasa.gov<mailto:kent.a.stednitz at nasa.gov>>; Astorga, Emigdio G. (ARC-JCM) <emigdio.g.astorga at nasa.gov<mailto:emigdio.g.astorga at nasa.gov>>; Berber, Daniel L. (ARC-JCM)[JACOBS] <daniel.l.berber at nasa.gov<mailto:daniel.l.berber at nasa.gov>>; Sethna, Shaina V. (ARC-JCM) <shaina.v.sethna at nasa.gov<mailto:shaina.v.sethna at nasa.gov>>
Subject: 6-3-22 N232 Project Updates
Hi All,
Below are the project updates for N232 as of 6/3/22. Please feel free to contact me if you have any questions or concerns.
Thank you,
Roxana
N232 Repair HP1-HP4 & RFS1 Booster Pump (CTO 1670443) – Vendors from the bid walk did not submit the required documents for award consideration. Jacobs reaching out to the vendors for documentation but this project will have to be rebid or an amendment added to solicit a proposal. After the project is awarded the CTO will route for approval signatures. Jacobs to notify FSM’s in advance if there will be any HVAC disruptions during the installation.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/all/attachments/20220621/1de8d7ea/attachment-0001.htm>
More information about the All
mailing list