[Aeromma-all] AEROMMA DC-8 Instrument Integration Meeting Notes 7 February 2023

Liem, Andrian (ARC-SGP)[Bay Area Environmental Research Institute] andrian.c.liem at nasa.gov
Tue Feb 7 12:42:34 PST 2023


Hello All,

Please see attached slides from today’s meeting and meeting notes below.


  *   Mission Registration
     *   Invitation has been sent, deadline to register 2/28
     *   Deployment/ Orientation Guides to be provided by end of February
     *   The Mission Calendar on ESPO AEROMMA page has been updated.
     *   DC-8 QNC Flight Clearance Process
        *   Flight Medical Clearance Process https://espo.nasa.gov/aeromma/content/AEROMMA_DC-8_Flight_Clearance
        *   Required forms attached



  *   Logistics
     *   ESPO provides standard gasses, consumable requirements survey will be sent by ESPO late February
     *   Shipping address to AFRC:



NASA ARMSTRONG

Attn: Jeff Nelms / 661-276-7447

Your Instrument Team Name

2825 East Ave P

Palmdale, CA 93550


o    Shipping to WPAFB: ESPO will ship to and from AFRC


  *   Aircraft and Instrument Status
     *   DC- 8 in maintenance with planned completion by 21 April
     *   ACES - no updates
     *   ACOS- No updates
     *   AMP- no updates
     *   AOP- no updates
     *   b-CIMS - on track, mounting hardware has gone out for quoting
     *   BRC PilS - no updates
     *   CAPS - on track
     *   CCN - part of AMP
     *   CSU- NH3- on track
     *   CT-CIMS- moving forward with ion source tests and re-racking the instrument
     *   DLH DACOM - on track
     *   HR-AMS- re-racking instrument and planning on putting instrument this week
     *   I-CIMS - on track
     *   ISAF- on track
     *   iWAS - no updates, will start populating DC-8 rack, working on safety requirements
     *   LGR- Picarro - on track
     *   LIF-SO2- Working on pressure system paperwork this week
     *   Li-Neph/TSINeph- on track, will need helium, have some to bring
     *   NNOx- instrument is on DC8 rack and on track
     *   NOyO3- on track
     *   OHR - on track, going to update the CAT model
     *   OPALS- on track
     *   PALMS-NG - on track
     *   PFP- in process of chemical integrity tests
     *   PilS-IC- on track
     *   PTR-Tof- instrument is on rack and working, need to work through the paperwork
     *   S-HIS- on track, working through pressure gas handling, documentation should be ready this week.
     *   SP2- on track
     *   VIA VOCUS - multi hardware has been ordered and will arrive in a couple of weeks
     *   J-CAFS- on track, have to produce the optical inlets and hope to get the design approved soon.


  *   PI Remarks (Carsten):
     *   Good to see all the progress, make sure everybody takes those emails as priority in their inbox and answers everything quickly. It’s always a snowball effect when one missing other thing can’t be worked on.
     *   Make sure you register and start medical clearance as soon as possible especially if you’re sure you’re flying.


Thank you for joining and participating in today’s meeting. Next meeting Feb 21.

Andrian Liem
Deputy PM - Earth Science Project Office (ESPO)
NASA Ames Research Center
Bay Area Environmental Research Institute (BAERI)
andrian.c.liem at nasa.gov<mailto:andrian.c.liem at nasa.gov>
+1.650.604.3172 office
+1.415.746.0555 mobile

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://espo.nasa.gov/pipermail/aeromma-all/attachments/20230207/9e8be370/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: AEROMMA DC-8 Bi-Weekly 7Feb23.pptx.pdf
Type: application/pdf
Size: 608930 bytes
Desc: AEROMMA DC-8 Bi-Weekly 7Feb23.pptx.pdf
URL: <http://espo.nasa.gov/pipermail/aeromma-all/attachments/20230207/9e8be370/attachment-0003.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: AEROMMA AFRC70176b.pdf
Type: application/pdf
Size: 42840 bytes
Desc: AEROMMA AFRC70176b.pdf
URL: <http://espo.nasa.gov/pipermail/aeromma-all/attachments/20230207/9e8be370/attachment-0004.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Hearing Conservation Acknowledgement.pdf
Type: application/pdf
Size: 171277 bytes
Desc: Hearing Conservation Acknowledgement.pdf
URL: <http://espo.nasa.gov/pipermail/aeromma-all/attachments/20230207/9e8be370/attachment-0005.pdf>


More information about the aeromma-all mailing list