Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

Associated content: 

ATTREX 02/11/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration/testing on schedule. Aircraft will be ready for Wt/Bal in the morning.
 
Accomplishments:

  • GHOST electrical harnesses installed.
  • Hawkeye harness/fibre end-end test completed
  • Worked MMS Heater EIP Cable
  • AIITS replacement Laser arrived – being installed (non-interference with Wt/Bal)

Concerns / Watch List:

ATTREX 02/12/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration/testing is on schedule. Wt/Bal completed. Outdoor IT Testing tomorrow.
P.I.’s please see revised show-time schedule below…
 
Accomplishments:

  • AIITS Laser re-installed and instrument is working
  • Hangar Data-IT Testing continued

Upcoming Schedule:

ATTREX 02/13/15 Mission Daily Schedule

Overview:

  • All instruments are now integrated on the aircraft
  • Outdoor Satcom Testing has begun

Accomplishments:

  • Outdoor Satcom testing, with Instrument teams in the GHOC has begun
  • NOAA O3 and NWV, MTP, and GWAS complete Iridium testing
  • All four instruments are complete with no testing planned on Tuesday
  • MMS, Hawkeye, AIITS testing has begun 

Issues/Watch items:

AIITS Pod final installation (2.18.15)

CAST hangar testing concludes (2.17.15)

GHOST Cryostat install after LN2 fill (2.17.15)

Nick Krause performing Hawkeye data system checkout (2.13.15)

MTP (Dick Denning and Prashanth Pandian) during Outdoor Satcom Testing (2.13.15)

GHOST Installation (2.10.15)

AIITS Ping Test (2.10.15)