Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Achievements August 29 and plans for August 30
UND/wing probes
PDI
HiGEAR
Data Systems
Schedule for August 30:
0800 hangar/labs open
0815 punch list meeting and a/c door open
1600 a/c power off
NLT 1615 – meeting to review work completed & tomorrow's plan
1630 mech/eng support ends
Kelly