Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

ORACLES 08/29/18 Mission Daily Schedule

Accomplishments August 28 and plans for August 29

UND/Cloud probes

  • Rack is populated and will be ready to load onto the plane sometime late morning.
  • Trying to locate a missing adaptor mount for one of the canisters, and exploring options for using a different one if it cannot be located.

PDI

  • Jennifer is waiting for her equipment to get back via FedEx.

HiGEAR

  • Steve and Amie ordered a replacement cable that should address their issue. When it arrives, they will do system checks. 

 
Data Systems

  • Litton should be ready for installation tomorrow 
  • Testing with cloud probes tomorrow

Kelly