Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Plan of the day for Saturday, February 15
For the long-term (forecasting and science) tentative plans, please refer to the Daily Science plan.
Project website: https://espo.nasa.gov/impacts
Project data catalog: http://impacts.atmos.washington.edu/
T-Shirts!! Wallops: See Dan. Hunter: See Bernie
First time at Wallops? See Dan and Kelly for the safety briefing.
All times are EST
IMPACTS General
Saturday, Feb 15
9:00 - 10:00: Daily Briefing (Wallops W162; Webex/Telecon)
Sunday, Feb 16
9:00 - 10:00: Daily Briefing (Wallops W162; Webex/Telecon)
IMPACTS P-3 - Wallops
Saturday, Feb 15
No A/C access, Lab Access
Sunday, Feb 16
No A/C access, Lab Access
IMPACTS ER-2 - Hunter
Saturday, Feb 15
Hard down day
Sunday, Feb 16
08:00 - 15:30 A/C Access
ESPO Crew on Deck
Wallops: Dan Chirica (650 318-8257), Caitlin Murphy (650-680-7732)
Hunter: Bernie Luna (650 417-8810)
IMPACTS Webex telecon : +844 467 4685 code: 804464#